PSM-I.001.048

Question 48

True or False: The Scrum Master is responsible for ensuring that the Development Team has a clear understanding of the work to be done.

TRUE

FALSE

Overall explanation

The Product Owner is responsible for ensuring that the Development Team has a clear understanding of the work to be done. The Product Owner collaborates with the Development Team during refinement activities to clarify the requirements and answer any ##### Questions they may have.

Domain

Roles