PSM-I.001.048
January 12, 2025
Question 48
True or False: The Scrum Master is responsible for ensuring that the Development Team has a clear understanding of the work to be done.
TRUE
FALSE
Overall explanation
The Product Owner is responsible for ensuring that the Development Team has a clear understanding of the work to be done. The Product Owner collaborates with the Development Team during refinement activities to clarify the requirements and answer any ##### Questions they may have.
Domain
Roles