PSM-I.001.047

Question 47

True or False: The Scrum Team should strive to deliver all the items in the Product Backlog by the end of the Sprint.

FALSE

TRUE

Overall explanation

The Scrum Team should strive to deliver a potentially releasable Increment of the product by the end of the Sprint, not necessarily all the items in the Product Backlog. The Product Backlog is a dynamic and evolving list that may have items reprioritized or added based on changing requirements and feedback.

Domain

Artifacts