PSM-I.001.046
Question 46
The Product Owner receives a request from a stakeholder to include a specific feature in the current Sprint. The feature was not previously discussed or prioritized. What should the Product Owner do?
Evaluate the feature’s alignment with the product vision and priorities before making a decision.
Include the feature in the current Sprint to address the stakeholder’s request.
Collaborate with the Development Team to estimate the effort required for implementing the feature.
Engage in a conversation with the stakeholder to understand the urgency and potential impact of the request.
Overall explanation
In this scenario, the Product Owner should engage in a conversation with the stakeholder to understand the urgency and potential impact of the request. They should then collaborate with the Development Team to estimate the effort required and evaluate the feature’s alignment with the product vision and priorities before making a decision.
Domain
Scrum