PSM-I.001.027

Question 27

True or False: The Product Owner can add new items to the Sprint Backlog during the Sprint if they deem it necessary.

FALSE

TRUE

Overall explanation

The Sprint Backlog is a forecast of the work that the Development Team believes it can complete during the Sprint. It should not be changed during the Sprint unless the Development Team and Product Owner collaborate and agree to adjust the scope.

Domain

Artifacts