PSM-I.001.015 The Sprint Backlog is a subset of the Product Backlog

Question 15

True or False: The Sprint Backlog is a subset of the Product Backlog that contains the items selected for the current Sprint.

FALSE

TRUE

Overall explanation

The Sprint Backlog is a subset of the Product Backlog that contains the items selected for the current Sprint. It represents the Development Team’s plan for delivering the Sprint Goal and creating a potentially releasable Increment.

Domain

Artifacts