PSM-I.001.013 The Development Team realizes during the Sprint that they won’t be able to complete all the planned
January 12, 2025
Question 13
The Development Team realizes during the Sprint that they won’t be able to complete all the planned Product Backlog items. What should they do?
-
Seek assistance from the Scrum Master to remove any obstacles.
-
Inform the stakeholders about the incomplete items and seek their guidance.
-
Continue with the remaining items and deliver what is completed.
-
Collaborate with the Product Owner to reprioritize and adjust the Sprint Backlog.
Overall explanation
In this scenario, the Development Team should collaborate with the Product Owner to reprioritize and adjust the Sprint Backlog based on the remaining capacity and the most valuable items. They should also seek assistance from the Scrum Master to remove any obstacles hindering their progress.
Domain
Scrum