PSM-I.001.068

Question 68

The Development Team is consistently unable to complete the selected Product Backlog items within the Sprint time frame. What should the Scrum Master do to address this issue?

Assign additional team members to support the Development Team during the Sprint.

Review and adjust the Definition of Done to ensure it accurately reflects the team’s expectations.

Suggest increasing the Sprint duration to provide more time for completing the work.

Facilitate a retrospective to identify potential causes and collaborate with the team on improvement strategies.

Overall explanation

In this scenario, the Scrum Master should facilitate a retrospective to identify potential causes for incomplete work and collaborate with the team on improvement strategies. They should also review and adjust the Definition of Done to ensure it accurately reflects the team’s expectations.

Domain

Scrum