PSM-I.001.065
January 12, 2025
Question 65
During the Daily Scrum, a Development Team member raises an issue that requires immediate attention from the Scrum Master and Product Owner. What should they do?
Assign a task to the Scrum Master and Product Owner to investigate and resolve the issue.
Discuss the issue briefly and agree to address it later outside of the Daily Scrum.
Note the issue and schedule a separate meeting after the Daily Scrum to address it.
Pause the Daily Scrum and resolve the issue as a team before continuing.
Overall explanation
In this scenario, the team should continue with the Daily Scrum and take it up further after the meeting.
Domain
Events