PSM-I.001.062
Question 62
The Development Team is unable to complete all the committed Product Backlog items by the end of the Sprint due to unforeseen challenges. What should they do in the Sprint Review?
Collaborate with the Product Owner to determine the best approach for incomplete items.
Seek an extension of the Sprint duration to complete the remaining items.
Present only the completed items and avoid mentioning the unfinished ones.
Discuss the completed items and the reasons for the unfinished ones, seeking stakeholder input.
Overall explanation
In this scenario, the Development Team should discuss the completed items and openly communicate the reasons for the unfinished ones during the Sprint Review. They should collaborate with the Product Owner to determine the best approach for incomplete items, considering stakeholder input and prioritization.
Domain
Events