{"id":26,"date":"2025-01-12T05:02:34","date_gmt":"2025-01-12T05:02:34","guid":{"rendered":"https:\/\/exam.kimson.us\/?p=26"},"modified":"2025-01-12T07:40:54","modified_gmt":"2025-01-12T07:40:54","slug":"psm-i-002-scrum-master-mock-exam-simulator-2","status":"publish","type":"post","link":"https:\/\/exam.kimson.us\/?p=26","title":{"rendered":"PSM-I.002 Scrum Master Mock Exam Simulator 2"},"content":{"rendered":"<h2>Scrum Master Mock Exam Simulator 2 &#8211; Results<\/h2>\n<p>Question 1<\/p>\n<p>What is the purpose of the Sprint Retrospective?<\/p>\n<p>To update the Product Backlog<\/p>\n<p>To discuss upcoming Sprint Backlog items<\/p>\n<p>Correct answer<\/p>\n<p>To inspect and adapt the Scrum Team<\/p>\n<p>To review the work completed in the Sprint<\/p>\n<p>Overall explanation<\/p>\n<p>The Sprint Retrospective focuses on inspecting and adapting the Scrum Team and its processes.<\/p>\n<p>Domain<\/p>\n<p>Sprint Retrospective<\/p>\n<p>Question 2<\/p>\n<p>During the Daily Scrum, who is required to attend?<\/p>\n<p>Stakeholders<\/p>\n<p>Correct answer<\/p>\n<p>Development Team<\/p>\n<p>Scrum Master<\/p>\n<p>Product Owner<\/p>\n<p>Overall explanation<\/p>\n<p>The Daily Scrum is for the Development Team to synchronize their work and plan for the next 24 hours.<\/p>\n<p>Domain<\/p>\n<p>Daily Scrum<\/p>\n<p>Question 3<\/p>\n<p>Who is responsible for managing the Sprint Backlog?<\/p>\n<p>Product Owner<\/p>\n<p>Scrum Master<\/p>\n<p>Correct answer<\/p>\n<p>Development Team<\/p>\n<p>Project Manager<\/p>\n<p>Overall explanation<\/p>\n<p>The Development Team is responsible for managing the Sprint Backlog and selecting work for the Sprint.<\/p>\n<p>Domain<\/p>\n<p>Sprint Backlog<\/p>\n<p>Question 4<\/p>\n<p>During a Sprint Retrospective, the Development Team identifies that they faced challenges in collaborating effectively. What action should they take?<\/p>\n<p>Blame each other for the lack of collaboration<\/p>\n<p>Request the Scrum Master to solve their collaboration issues<\/p>\n<p>Ignore the issue and continue working as usual<\/p>\n<p>Correct answer<\/p>\n<p>Reflect on their collaboration practices and discuss improvements<\/p>\n<p>Overall explanation<\/p>\n<p>The Development Team should reflect on their collaboration practices and discuss improvements as the sprint retrospective is the appropriate forum dedicated to discussing what went well and what can be improved in a sprint.<\/p>\n<p>Domain<\/p>\n<p>Sprint Retrospective<\/p>\n<p>Question 5<\/p>\n<p>Who is responsible for ensuring the Development Team understands the Product Backlog items?<\/p>\n<p>Correct answer<\/p>\n<p>Product Owner<\/p>\n<p>Development Team<\/p>\n<p>Stakeholders<\/p>\n<p>Scrum Master<\/p>\n<p>Overall explanation<\/p>\n<p>Scrum Product Owners understand the customer and business requirements, then create and manage the product backlog based on those requirements. The Product Owner are responsible for any clarification regarding the PBIs.<\/p>\n<p>Domain<\/p>\n<p>Development Team<\/p>\n<p>Question 6<\/p>\n<p>What happens when the Sprint duration is too short?<\/p>\n<p>The Product Owner needs to extend the timebox<\/p>\n<p>The Scrum Team must work faster<\/p>\n<p>The Sprint becomes less flexible<\/p>\n<p>Correct answer<\/p>\n<p>The Scrum Team reduces the scope<\/p>\n<p>Overall explanation<\/p>\n<p>When the Sprint duration is too short, the Scrum Team should reduce the scope rather than extend the timebox.<\/p>\n<p>Domain<\/p>\n<p>Sprint<\/p>\n<p>Question 7<\/p>\n<p>The Development Team estimates that a User Story will take more time to complete than originally planned. What should the Development Team do?<\/p>\n<p>Seek assistance from the Scrum Master to speed up the work and meet the original estimate<\/p>\n<p>Adjust the estimate without informing the Product Owner<\/p>\n<p>Correct answer<\/p>\n<p>Communicate the updated estimate to the Product Owner and collaborate on potential solutions<\/p>\n<p>Ignore the updated estimate and continue working based on the original plan<\/p>\n<p>Overall explanation<\/p>\n<p>The Development Team should communicate the updated estimate to the Product Owner and collaborate on potential solutions.<\/p>\n<p>Domain<\/p>\n<p>Development Team<\/p>\n<p>Question 8<\/p>\n<p>When should the Product Owner participate in the Daily Scrum?<\/p>\n<p>At the beginning of the meeting<\/p>\n<p>Correct answer<\/p>\n<p>The Product Owner should not attend<\/p>\n<p>At the end of the meeting<\/p>\n<p>Only when there are issues to discuss<\/p>\n<p>Overall explanation<\/p>\n<p>The Product Owner is not required to attend the Daily Scrum as it is primarily for the Development Team.<\/p>\n<p>Domain<\/p>\n<p>Daily Scrum<\/p>\n<p>Question 9<\/p>\n<p>What does the Scrum Master do during the Sprint?<\/p>\n<p>Assigns work to the Development Team<\/p>\n<p>Collaborates with the Product Owner<\/p>\n<p>Provides updates to stakeholders<\/p>\n<p>Correct answer<\/p>\n<p>Ensures everyone follows the Scrum process<\/p>\n<p>Overall explanation<\/p>\n<p>The Scrum Master ensures adherence to the Scrum framework and supports the team in following the process.<\/p>\n<p>Domain<\/p>\n<p>Scrum Master<\/p>\n<p>Question 10<\/p>\n<p>True or False: The Sprint Backlog is a dynamic document that is updated throughout the Sprint.<\/p>\n<p>Correct answer<\/p>\n<p>TRUE<\/p>\n<p>FALSE<\/p>\n<p>Overall explanation<\/p>\n<p>The Sprint Backlog is a dynamic document that is updated throughout the Sprint as the work progresses.<\/p>\n<p>Domain<\/p>\n<p>Sprint Backlog<\/p>\n<p>Question 11<\/p>\n<p>How often should the Scrum Team hold a Sprint Retrospective?<\/p>\n<p>Once a year<\/p>\n<p>Once a month<\/p>\n<p>Every other Sprint<\/p>\n<p>Correct answer<\/p>\n<p>After every Sprint<\/p>\n<p>Overall explanation<\/p>\n<p>The Scrum Team should hold a Sprint Retrospective after every Sprint to reflect and improve.<\/p>\n<p>Domain<\/p>\n<p>Sprint Retrospective<\/p>\n<p>Question 12<\/p>\n<p>Management has the authority to cancel a Sprint?<\/p>\n<p>TRUE<\/p>\n<p>Correct answer<\/p>\n<p>FALSE<\/p>\n<p>Overall explanation<\/p>\n<p>Only the Product Owner has the authority to cancel a Sprint if the Sprint Goal becomes obsolete.<\/p>\n<p>Domain<\/p>\n<p>Sprint<\/p>\n<p>Question 13<\/p>\n<p>What is the recommended maximum duration for a Sprint Review?<\/p>\n<p>1 hour<\/p>\n<p>30 minutes<\/p>\n<p>2 hours<\/p>\n<p>Correct answer<\/p>\n<p>4 hours<\/p>\n<p>Overall explanation<\/p>\n<p>Sprint reviews are limited to a maximum of\u00a0<strong>four hours<\/strong>. The general rule of thumb is to allow one hour for sprint review every one week of sprint length. That means teams should timebox sprint review to two hours for a two-week sprint and four hours for a one-month sprint.<\/p>\n<p>Domain<\/p>\n<p>Sprint Review<\/p>\n<p>Question 14<\/p>\n<p>In Scrum, what is the purpose of the Sprint Review?<\/p>\n<p>To present the completed User Stories and demonstrate the working product to management.<\/p>\n<p>To discuss and address any issues or impediments that are blocking progress<\/p>\n<p>To inspect the progress toward the Sprint Goal and adapt the plan as necessary<\/p>\n<p>Correct answer<\/p>\n<p>To review\u00a0 the work completed by the Development Team and get feedback from stakeholders.<\/p>\n<p>Overall explanation<\/p>\n<p>The sprint review&#8217;s purpose is to inspect the increment that was developed in that sprint and collect feedback from key stakeholders.<\/p>\n<p>Domain<\/p>\n<p>Sprint Review<\/p>\n<p>Question 15<\/p>\n<p>True or False: The Sprint Review is an opportunity for the Product Owner to inspect the increment and adapt the Product Backlog.<\/p>\n<p>FALSE<\/p>\n<p>Correct answer<\/p>\n<p>TRUE<\/p>\n<p>Overall explanation<\/p>\n<p>The Sprint Review is an opportunity for the Product Owner to inspect the increment and adapt the Product Backlog based on the feedback and insights gained.<\/p>\n<p>Domain<\/p>\n<p>Sprint Review<\/p>\n<p>Question 16<\/p>\n<p>What does the Scrum Master do during Sprint Planning?<\/p>\n<p>Correct answer<\/p>\n<p>Facilitates the meeting<\/p>\n<p>Assigns tasks to the Development Team<\/p>\n<p>Provides estimates for the Product Backlog<\/p>\n<p>Sets the Sprint Goal<\/p>\n<p>Overall explanation<\/p>\n<p>The Scrum Master facilitates Sprint Planning to ensure it is effective and timeboxed.<\/p>\n<p>Domain<\/p>\n<p>Sprint Planning<\/p>\n<p>Question 17<\/p>\n<p>During a Sprint Review, the Product Owner presents a User Story that does not meet the Definition of Done. What action should the Scrum Master take?<\/p>\n<p>Ignore the issue and proceed with the Sprint Review without addressing the incomplete User Story<\/p>\n<p>Correct answer<\/p>\n<p>Facilitate a discussion to understand why the User Story does not meet the Definition of Done and encourage improvements<\/p>\n<p>Request the Development Team to immediately complete the User Story to meet the Definition of Done<\/p>\n<p>Encourage the Product Owner to adjust the Definition of Done to include the incomplete User Story<\/p>\n<p>Overall explanation<\/p>\n<p>The Scrum Master should facilitate a discussion to understand why the User Story does not meet the Definition of Done and encourage improvements.<\/p>\n<p>Domain<\/p>\n<p>Sprint Review<\/p>\n<p>Question 18<\/p>\n<p>True or False: The Product Owner is responsible for creating and maintaining the Sprint Backlog.<\/p>\n<p>Correct answer<\/p>\n<p>FALSE<\/p>\n<p>TRUE<\/p>\n<p>Overall explanation<\/p>\n<p>The Development Team is responsible for creating and maintaining the Sprint Backlog.<\/p>\n<p>Domain<\/p>\n<p>Product Owner\/Development Team<\/p>\n<p>Question 19<\/p>\n<p>What is the role of the Scrum Master during the Sprint?<\/p>\n<p>Correct answer<\/p>\n<p>To protect the Development Team<\/p>\n<p>To assign tasks to the Development Team<\/p>\n<p>To review and approve the Increment<\/p>\n<p>To make decisions on behalf of the team<\/p>\n<p>Overall explanation<\/p>\n<p>The Scrum Master&#8217;s role includes protecting the Development Team and ensuring adherence to Scrum.<\/p>\n<p>Domain<\/p>\n<p>Scrum Master<\/p>\n<p>Question 20<\/p>\n<p>Who is responsible for removing impediments?<\/p>\n<p>Product Owner<\/p>\n<p>Correct answer<\/p>\n<p>Scrum Master<\/p>\n<p>Stakeholders<\/p>\n<p>Development Team<\/p>\n<p>Overall explanation<\/p>\n<p>The Scrum Master is responsible for removing impediments that hinder the Development Team&#8217;s progress.<\/p>\n<p>Domain<\/p>\n<p>Scrum Master<\/p>\n<p>Question 21<\/p>\n<p>True or False: Scrum can only be used for software development projects.<\/p>\n<p>Correct answer<\/p>\n<p>FALSE<\/p>\n<p>TRUE<\/p>\n<p>Overall explanation<\/p>\n<p>Scrum can be used in various domains and is not limited to software development projects.<\/p>\n<p>Domain<\/p>\n<p>General Scrum Concepts<\/p>\n<p>Question 22<\/p>\n<p>During the Daily Scrum, one team member mentions a technical issue that is blocking their progress. What should the Development Team do?<\/p>\n<p>Assign the Scrum Master to address the technical issue and unblock the team member<\/p>\n<p>Correct answer<\/p>\n<p>Collaborate as a team to identify potential solutions and remove the technical issue<\/p>\n<p>Ignore the technical issue and focus on completing other tasks<\/p>\n<p>Inform the Product Owner and request their assistance in resolving the technical issue<\/p>\n<p>Overall explanation<\/p>\n<p>The Development Team should collaborate as a team to identify potential solutions and remove the technical issue.<\/p>\n<p>Domain<\/p>\n<p>Daily Scrum<\/p>\n<p>Question 23<\/p>\n<p>As a Scrum Master, you notice that the Development Team is not collaborating effectively. What action should you take?<\/p>\n<p>Reassign team members to different projects or teams to mitigate the collaboration issues<\/p>\n<p>Correct answer<\/p>\n<p>Facilitate a retrospective to identify the root causes of the collaboration issues and work with the team to address them<\/p>\n<p>Provide training to the team members on collaboration techniques and best practices<\/p>\n<p>Assign tasks to individual team members to ensure they stay focused on their responsibilities<\/p>\n<p>Overall explanation<\/p>\n<p>The Scrum Master should facilitate a retrospective to identify the underlying issues and work with the team to address them.<\/p>\n<p>Domain<\/p>\n<p>Scrum Master<\/p>\n<p>Question 24<\/p>\n<p>What is the recommended timebox for the Daily Scrum?<\/p>\n<p>30 minutes<\/p>\n<p>60 minutes<\/p>\n<p>45 minutes<\/p>\n<p>Correct answer<\/p>\n<p>15 minutes<\/p>\n<p>Overall explanation<\/p>\n<p>The Daily Scrum should be timeboxed to 15 minutes to keep it focused and efficient.<\/p>\n<p>Domain<\/p>\n<p>Daily Scrum<\/p>\n<p>Question 25<\/p>\n<p>True or False: The Sprint Goal is a commitment made by the Product Owner to the stakeholders.<\/p>\n<p>Correct answer<\/p>\n<p>FALSE<\/p>\n<p>TRUE<\/p>\n<p>Overall explanation<\/p>\n<p>The Sprint Goal is the single objective for the Sprint. Although the Sprint Goal is a commitment by the Developers, it provides flexibility in terms of the exact work needed to achieve it.<\/p>\n<p>Domain<\/p>\n<p>Sprint Goal<\/p>\n<p>Question 26<\/p>\n<p>What is the purpose of the Daily Scrum event in Scrum?<\/p>\n<p>Correct answer<\/p>\n<p>To inspect and adapt the progress towards the Sprint Goal<\/p>\n<p>To identify potential risks and issues<\/p>\n<p>To plan the work for the day<\/p>\n<p>To provide a status update to stakeholders<\/p>\n<p>Overall explanation<\/p>\n<p>The purpose of the Daily Scrum is to inspect and adapt the progress towards the Sprint Goal, foster collaboration, and identify any obstacles or adjustments needed to achieve the goal.<\/p>\n<p>Domain<\/p>\n<p>Daily Scrum<\/p>\n<p>Question 27<\/p>\n<p>Who is responsible for ensuring the Scrum Team understands Scrum?<\/p>\n<p>Stakeholders<\/p>\n<p>Product Owner<\/p>\n<p>Correct answer<\/p>\n<p>Scrum Master<\/p>\n<p>Development Team<\/p>\n<p>Overall explanation<\/p>\n<p>The Scrum Master is responsible for ensuring the Scrum Team understands and follows Scrum practices.<\/p>\n<p>Domain<\/p>\n<p>Scrum Master<\/p>\n<p>Question 28<\/p>\n<p>The Development Team estimates that a User Story will take 10 story points to complete. However, during the Sprint, they realize it will take longer. What should they do?<\/p>\n<p>Drop the User Story from the Sprint and focus on completing other User Stories within the time frame<\/p>\n<p>Continue working on the User Story and put in extra effort to complete it within the original time estimate<\/p>\n<p>Correct answer<\/p>\n<p>Communicate the delay to the Product Owner and collaborate to reprioritize the User Story or adjust the Sprint Backlog<\/p>\n<p>Inform the Scrum Master and request an extension to the Sprint duration to accommodate the additional time required<\/p>\n<p>Overall explanation<\/p>\n<p>The Development Team should communicate the delay to the Product Owner and collaborate to reprioritize the User Story or adjust the Sprint Backlog.<\/p>\n<p>Domain<\/p>\n<p>Development Team<\/p>\n<p>Question 29<\/p>\n<p>What is the primary role of the Product Owner?<\/p>\n<p>To create the Sprint Backlog<\/p>\n<p>To manage the Development Team<\/p>\n<p>To enforce the Definition of Done<\/p>\n<p>Correct answer<\/p>\n<p>To represent the stakeholders&#8217; interests<\/p>\n<p>Overall explanation<\/p>\n<p>The primary role of the Product Owner is to represent the stakeholders&#8217; interests and maximize value.<\/p>\n<p>Domain<\/p>\n<p>Product Owner<\/p>\n<p>Question 30<\/p>\n<p>What is the purpose of the Sprint Review?<\/p>\n<p>Correct answer<\/p>\n<p>To inspect the Increment<\/p>\n<p>To review and approve changes<\/p>\n<p>To update the Sprint Backlog<\/p>\n<p>To discuss upcoming work<\/p>\n<p>Overall explanation<\/p>\n<p>The Sprint Review is an opportunity to inspect the Increment and adapt the Product Backlog.<\/p>\n<p>Domain<\/p>\n<p>Sprint Review<\/p>\n<p>Question 31<\/p>\n<p>True or False: The Sprint Backlog is a dynamic document that is updated throughout the Sprint by the Scrum Master.<\/p>\n<p>TRUE<\/p>\n<p>Correct answer<\/p>\n<p>FALSE<\/p>\n<p>Overall explanation<\/p>\n<p>The Sprint Backlog is a dynamic document that is updated as the Development Team works on the selected User Stories. However, Scrum Master is not responsible for making any updates to the Sprint Backlog.<\/p>\n<p>Domain<\/p>\n<p>Sprint Backlog<\/p>\n<p>Question 32<\/p>\n<p>The Product Owner informs the Scrum Master that they are facing difficulties in managing the Product Backlog. What should the Scrum Master do?<\/p>\n<p>Correct answer<\/p>\n<p>Coach the Product Owner on effective Product Backlog management practices<\/p>\n<p>Ignore the issue and let the Product Owner handle it on their own<\/p>\n<p>Assign a team member to assist the Product Owner in managing the Product Backlog<\/p>\n<p>Take over the Product Owner&#8217;s responsibilities and manage the Product Backlog<\/p>\n<p>Overall explanation<\/p>\n<p>The Scrum Master should coach the Product Owner on effective Product Backlog management practices.<\/p>\n<p>Domain<\/p>\n<p>Product Owner<\/p>\n<p>Question 33<\/p>\n<p>What is the recommended maximum duration for a Daily Scrum?<\/p>\n<p>45 minutes<\/p>\n<p>Correct answer<\/p>\n<p>15 minutes<\/p>\n<p>1 hour<\/p>\n<p>30 minutes<\/p>\n<p>Overall explanation<\/p>\n<p>The recommended maximum duration for a Daily Scrum is 15 minutes. It allows for effective coordination and ensures the event does not become a lengthy status update meeting.<\/p>\n<p>Domain<\/p>\n<p>Daily Scrum<\/p>\n<p>Question 34<\/p>\n<p>Who is responsible for ordering the Product Backlog?<\/p>\n<p>Scrum Master<\/p>\n<p>Correct answer<\/p>\n<p>Product Owner<\/p>\n<p>Stakeholders<\/p>\n<p>Development Team<\/p>\n<p>Overall explanation<\/p>\n<p>The Product Owner is responsible for ordering the Product Backlog based on value and priorities.<\/p>\n<p>Domain<\/p>\n<p>Product Backlog<\/p>\n<p>Question 35<\/p>\n<p>The Product Owner wants to add new User Stories to the current Sprint. What should the Development Team do?<\/p>\n<p>Request the Scrum Master to make the decision on behalf of the Development Team<\/p>\n<p>Correct answer<\/p>\n<p>Collaborate with the Product Owner to assess the impact on the Sprint Goal and decide whether to add the User Stories<\/p>\n<p>Reject the Product Owner&#8217;s request to add new User Stories<\/p>\n<p>Add the new User Stories without considering the impact on the current Sprint<\/p>\n<p>Overall explanation<\/p>\n<p>The Development Team should collaborate with the Product Owner to assess the impact on the Sprint Goal and decide whether to add the User Stories.<\/p>\n<p>Domain<\/p>\n<p>Development Team<\/p>\n<p>Question 36<\/p>\n<p>In Scrum, the organizational management is responsible for tracking the progress of work and ensuring that the Sprint Goal is achieved?<\/p>\n<p>TRUE<\/p>\n<p>Correct answer<\/p>\n<p>FALSE<\/p>\n<p>Overall explanation<\/p>\n<p>The Development Team is responsible for tracking the progress of work and ensuring that the Sprint Goal is achieved.<\/p>\n<p>Domain<\/p>\n<p>Development Team<\/p>\n<p>Question 37<\/p>\n<p>True or False: The Scrum framework prescribes specific roles and responsibilities for the Scrum Team members.<\/p>\n<p>Correct answer<\/p>\n<p>TRUE<\/p>\n<p>FALSE<\/p>\n<p>Overall explanation<\/p>\n<p>The Scrum framework prescribes specific roles and responsibilities, including the Scrum Master, Product Owner, and Development Team, to ensure effective collaboration and value delivery.<\/p>\n<p>Domain<\/p>\n<p>Scrum Framework<\/p>\n<p>Question 38<\/p>\n<p>Who is responsible for managing the Product Backlog and ensuring that it is transparent, ordered, and properly refined?<\/p>\n<p>Stakeholders<\/p>\n<p>Development Team<\/p>\n<p>Correct answer<\/p>\n<p>Product Owner<\/p>\n<p>Scrum Master<\/p>\n<p>Overall explanation<\/p>\n<p>The Product Owner is responsible for managing the Product Backlog and ensuring it is transparent, ordered, and properly refined to maximize value delivery.<\/p>\n<p>Domain<\/p>\n<p>Product Backlog<\/p>\n<p>Question 39<\/p>\n<p>What is the purpose of the Sprint Retrospective?<\/p>\n<p>Correct answer<\/p>\n<p>To inspect and adapt the Scrum Team<\/p>\n<p>To discuss upcoming Sprint Backlog items<\/p>\n<p>To update the Product Backlog<\/p>\n<p>To review the work completed in the Sprint<\/p>\n<p>Overall explanation<\/p>\n<p>The Sprint Retrospective focuses on inspecting and adapting the Scrum Team and its processes.<\/p>\n<p>Domain<\/p>\n<p>Sprint Retrospective<\/p>\n<p>Question 40<\/p>\n<p>The Product Owner wants to cancel a Sprint midway due to a change in business priorities. What should the Scrum Master do?<\/p>\n<p>Correct answer<\/p>\n<p>Explain the impact of canceling the Sprint and facilitate a discussion on alternative options<\/p>\n<p>Escalate the issue to senior management and let them decide whether to cancel the Sprint<\/p>\n<p>Force the Product Owner to continue the Sprint despite the change in priorities<\/p>\n<p>Cancel the Sprint immediately without any discussion<\/p>\n<p>Overall explanation<\/p>\n<p>The Scrum Master should explain the impact of canceling the Sprint and facilitate a discussion on alternative options.<\/p>\n<p>Domain<\/p>\n<p>Scrum Master<\/p>\n<p>Question 41<\/p>\n<p>The Product Owner receives a high-priority request from a stakeholder that may disrupt the current Sprint Goal. What should the Product Owner do?<\/p>\n<p>Immediately add the request to the current Sprint without assessing its impact<\/p>\n<p>Reject the request and continue with the current Sprint Goal<\/p>\n<p>Consult the Scrum Master to make the decision on whether to accept the request<\/p>\n<p>Correct answer<\/p>\n<p>Discuss the request with the stakeholders and evaluate its impact on the Sprint Goal<\/p>\n<p>Overall explanation<\/p>\n<p>The Product Owner should discuss the request with the stakeholders and evaluate its impact on the Sprint Goal.<\/p>\n<p>Domain<\/p>\n<p>Product Owner<\/p>\n<p>Question 42<\/p>\n<p>Who is responsible for facilitating the Sprint Planning event?<\/p>\n<p>Product Owner<\/p>\n<p>Development Team<\/p>\n<p>Stakeholders<\/p>\n<p>Correct answer<\/p>\n<p>Scrum Master<\/p>\n<p>Overall explanation<\/p>\n<p>The Scrum Master is responsible for facilitating the Sprint Planning event, ensuring the event is effective, timeboxed, and focuses on achieving the Sprint Goal.<\/p>\n<p>Domain<\/p>\n<p>Scrum Master Role<\/p>\n<p>Question 43<\/p>\n<p>The Development Team has just completed the work for a Sprint and is planning to start a new Sprint immediately. However, the Scrum Master suggests taking a short break before starting the next Sprint. What is the role of the Scrum Master in this situation?<\/p>\n<p>The Scrum Master should consult with the stakeholders and seek their approval before making a decision<\/p>\n<p>The Scrum Master should adhere to the Development Team&#8217;s decision and start the new Sprint immediately<\/p>\n<p>The Scrum Master should consult with the Product Owner and take their input before making a decision<\/p>\n<p>Correct answer<\/p>\n<p>The Scrum Master is responsible for facilitating the team&#8217;s self-organization and well-being, including suggesting breaks to maintain a healthy work-life balance<\/p>\n<p>Overall explanation<\/p>\n<p>The Scrum Master is responsible for facilitating the team&#8217;s self-organization and well-being, including suggesting breaks to maintain a healthy work-life balance.<\/p>\n<p>Domain<\/p>\n<p>Scrum Master<\/p>\n<p>Question 44<\/p>\n<p>The Product Owner realizes that there is a critical change in business requirements that has resulted in making the Sprint Goal obsolete. What the Product Owner do?<\/p>\n<p>Correct answer<\/p>\n<p>Discuss with the Scrum Team and cancel the Sprint.<\/p>\n<p>Extend the Sprint duration to accommodate the additional work caused by the change<\/p>\n<p>Reject the change and continue with the original Sprint Goal<\/p>\n<p>Collaborate with the Development Team to assess the impact of the change and adjust the Sprint Goal and backlog accordingly<\/p>\n<p>Overall explanation<\/p>\n<p>A Sprint can be cancelled before the Sprint time-box is over. Only the Product Owner has the authority to cancel the Sprint, although he or she may do so under influence from the stakeholders, the Development Team, or the Scrum Master. A Sprint would be cancelled if the Sprint Goal becomes obsolete.<\/p>\n<p>Domain<\/p>\n<p>Product Owner<\/p>\n<p>Question 45<\/p>\n<p>Who is responsible for tracking progress toward the Sprint Goal?<\/p>\n<p>Scrum Master<\/p>\n<p>Stakeholders<\/p>\n<p>Product Owner<\/p>\n<p>Correct answer<\/p>\n<p>Development Team<\/p>\n<p>Overall explanation<\/p>\n<p>The Development Team is responsible for tracking progress toward the Sprint Goal during the Sprint.<\/p>\n<p>Domain<\/p>\n<p>Sprint Goal<\/p>\n<p>Question 46<\/p>\n<p>What happens when the Sprint Goal becomes obsolete?<\/p>\n<p>The Development Team creates a new goal<\/p>\n<p>The Product Owner adjusts the scope<\/p>\n<p>The Scrum Master intervenes<\/p>\n<p>Correct answer<\/p>\n<p>The Sprint is canceled<\/p>\n<p>Overall explanation<\/p>\n<p>When the Sprint Goal becomes obsolete, the Sprint is typically canceled, and a new Sprint is started.<\/p>\n<p>Domain<\/p>\n<p>Sprint Goal<\/p>\n<p>Question 47<\/p>\n<p>Who is responsible for managing the Product Backlog?<\/p>\n<p>Development Team<\/p>\n<p>Scrum Master<\/p>\n<p>Project Manager<\/p>\n<p>Correct answer<\/p>\n<p>Product Owner<\/p>\n<p>Overall explanation<\/p>\n<p>The Product Owner is responsible for managing the Product Backlog and its contents.<\/p>\n<p>Domain<\/p>\n<p>Product Backlog<\/p>\n<p>Question 48<\/p>\n<p>The Product Owner wants to prioritize a new feature that was not initially planned for the current Sprint. What should the Development Team do?<\/p>\n<p>Correct answer<\/p>\n<p>Inform the Product Owner that the new feature cannot be accommodated in the current Sprint and discuss the possibility of adding it to a future Sprint<\/p>\n<p>Assign additional resources to work on the new feature and ensure it is completed within the current Sprint<\/p>\n<p>Accept the new feature and adjust the Sprint Backlog to include it<\/p>\n<p>Reject the new feature and continue working on the planned User Stories<\/p>\n<p>Overall explanation<\/p>\n<p>The Development Team should inform the Product Owner that the new feature cannot be accommodated in the current Sprint.<\/p>\n<p>Domain<\/p>\n<p>Product Owner<\/p>\n<p>Question 49<\/p>\n<p>During a Sprint Retrospective, the Development Team identifies that their Sprint Burndown Chart shows a consistent increase in remaining work. What action should the Scrum Master take?<\/p>\n<p>Extend the Sprint duration to accommodate the increasing workload<\/p>\n<p>Correct answer<\/p>\n<p>Facilitate a discussion to identify the root causes of the increasing trend and work with the team to find solutions<\/p>\n<p>Encourage the Development Team to work longer hours and complete the remaining work<\/p>\n<p>Adjust the remaining work estimates for the User Stories to align with the actual progress<\/p>\n<p>Overall explanation<\/p>\n<p>The Scrum Master should facilitate a discussion to identify the root causes of the increasing trend and work with the team to find solutions.<\/p>\n<p>Domain<\/p>\n<p>Sprint Retrospective<\/p>\n<p>Question 50<\/p>\n<p>When does the Sprint Review take place?<\/p>\n<p>Throughout the Sprint<\/p>\n<p>Correct answer<\/p>\n<p>At the end of the Sprint<\/p>\n<p>After the Daily Scrum<\/p>\n<p>At the beginning of the Sprint<\/p>\n<p>Overall explanation<\/p>\n<p>The Sprint Review takes place at the end of the Sprint to inspect the Increment and adapt the Product Backlog.<\/p>\n<p>Domain<\/p>\n<p>Sprint Review<\/p>\n<p>Question 51<\/p>\n<p>Who is responsible for creating the Sprint Backlog?<\/p>\n<p>Product Owner<\/p>\n<p>Correct answer<\/p>\n<p>Development Team<\/p>\n<p>Scrum Master<\/p>\n<p>Stakeholders<\/p>\n<p>Overall explanation<\/p>\n<p>The Development Team creates the Sprint Backlog during Sprint Planning based on the Product Backlog.<\/p>\n<p>Domain<\/p>\n<p>Sprint Backlog<\/p>\n<p>Question 52<\/p>\n<p>True or False: The Scrum framework prescribes specific engineering practices and techniques.<\/p>\n<p>TRUE<\/p>\n<p>Correct answer<\/p>\n<p>FALSE<\/p>\n<p>Overall explanation<\/p>\n<p>The Scrum framework does not prescribe specific engineering practices and techniques. It focuses on the roles, events, artifacts, and values of Scrum.<\/p>\n<p>Domain<\/p>\n<p>Scrum Framework<\/p>\n<p>Question 53<\/p>\n<p>True or False: The Product Owner is responsible for assigning tasks to the Development Team members during the Sprint.<\/p>\n<p>Correct answer<\/p>\n<p>FALSE<\/p>\n<p>TRUE<\/p>\n<p>Overall explanation<\/p>\n<p>The Product Owner is not responsible for assigning tasks to the Development Team members. It is the self-organizing nature of the Development Team.<\/p>\n<p>Domain<\/p>\n<p>Scrum Master<\/p>\n<p>Question 54<\/p>\n<p>What is the recommended frequency of Sprint Retrospectives?<\/p>\n<p>Every other Sprint<\/p>\n<p>Once a year<\/p>\n<p>Correct answer<\/p>\n<p>After every Sprint<\/p>\n<p>Once a month<\/p>\n<p>Overall explanation<\/p>\n<p>The Sprint Retrospective should be held after every Sprint to inspect and adapt the Scrum Team.<\/p>\n<p>Domain<\/p>\n<p>Sprint Retrospective<\/p>\n<p>Question 55<\/p>\n<p>True or False: The Daily Scrum is a status meeting where the Scrum Master provides updates on behalf of the Development Team.<\/p>\n<p>Correct answer<\/p>\n<p>FALSE<\/p>\n<p>TRUE<\/p>\n<p>Overall explanation<\/p>\n<p>The Daily Scrum is a meeting where the Development Team provides updates to each other, not the Scrum Master providing updates on their behalf.<\/p>\n<p>Domain<\/p>\n<p>Daily Scrum<\/p>\n<p>Question 56<\/p>\n<p>During Daily Scrum, the Developers plan the work for the next 72 hours.<\/p>\n<p>Correct answer<\/p>\n<p>FALSE<\/p>\n<p>TRUE<\/p>\n<p>Overall explanation<\/p>\n<p>Daily scrums are quick meetings held each day at the same time for members of the product development team working on a particular sprint. The team collectively reviews the progress made toward achieving the Sprint Goal. The focus is on the next 24 hours and not 72 hours.<\/p>\n<p>Domain<\/p>\n<p>Development Team<\/p>\n<p>Question 57<\/p>\n<p>During a Daily Scrum, a Development Team member mentions an issue that needs assistance from another team. What should they do?<\/p>\n<p>Ask the Product Owner to coordinate with the other team to resolve the issue<\/p>\n<p>Ignore the issue and hope that the other team will resolve it<\/p>\n<p>Collaborate with the team member to find a solution within the Development Team<\/p>\n<p>Correct answer<\/p>\n<p>Raise the issue to the Scrum Master to address the inter-team dependency<\/p>\n<p>Overall explanation<\/p>\n<p>The Development Team member should raise the issue to the Scrum Master to address the inter-team dependency.<\/p>\n<p>Domain<\/p>\n<p>Daily Scrum<\/p>\n<p>Question 58<\/p>\n<p>Who can cancel a Sprint?<\/p>\n<p>Correct answer<\/p>\n<p>Product Owner<\/p>\n<p>Stakeholders<\/p>\n<p>Development Team<\/p>\n<p>Scrum Master<\/p>\n<p>Overall explanation<\/p>\n<p>The Product Owner has the authority to cancel a Sprint if the Sprint Goal becomes obsolete.<\/p>\n<p>Domain<\/p>\n<p>Sprint<\/p>\n<p>Question 59<\/p>\n<p>During a Sprint, the Development Team realizes that they need to acquire new skills to complete the User Stories. What should they do?<\/p>\n<p>Request external training for the required skills<\/p>\n<p>Correct answer<\/p>\n<p>Collaborate with the Product Owner to adjust the Sprint Backlog and acquire the necessary skills<\/p>\n<p>Reject the User Stories that require new skills and focus on the ones they are familiar with<\/p>\n<p>Continue working on the User Stories and hope that they can learn the required skills as they progress<\/p>\n<p>Overall explanation<\/p>\n<p>The Development Team should collaborate with the Product Owner to adjust the Sprint Backlog and acquire the necessary skills.<\/p>\n<p>Domain<\/p>\n<p>Development Team<\/p>\n<p>Question 60<\/p>\n<p>True or False: The Scrum Master is responsible for removing impediments and ensuring that the Scrum Team follows the Scrum framework.<\/p>\n<p>FALSE<\/p>\n<p>Correct answer<\/p>\n<p>TRUE<\/p>\n<p>Overall explanation<\/p>\n<p>The Scrum Master is responsible for removing impediments and ensuring that the Scrum Team follows the Scrum framework.<\/p>\n<p>Domain<\/p>\n<p>Scrum Master<\/p>\n<p>Question 61<\/p>\n<p>True or False: The Scrum Master ensures that the Development Team follows the Scrum process and rules.<\/p>\n<p>Correct answer<\/p>\n<p>TRUE<\/p>\n<p>FALSE<\/p>\n<p>Overall explanation<\/p>\n<p>The Scrum Master is responsible for ensuring that the Development Team follows the Scrum process and rules.<\/p>\n<p>Domain<\/p>\n<p>Scrum Master<\/p>\n<p>Question 62<\/p>\n<p>What happens when the Sprint duration is too long?<\/p>\n<p>Correct answer<\/p>\n<p>The Scrum Team reduces the scope<\/p>\n<p>The Product Owner needs to extend the timebox<\/p>\n<p>The Scrum Team must work overtime<\/p>\n<p>The Sprint becomes more flexible<\/p>\n<p>Overall explanation<\/p>\n<p>When the Sprint duration is too long, the Scrum Team should reduce the scope rather than extend the timebox.<\/p>\n<p>Domain<\/p>\n<p>Sprint<\/p>\n<p>Question 63<\/p>\n<p>How often should the Product Backlog be prioritized?<\/p>\n<p>Only when requested by stakeholders<\/p>\n<p>Correct answer<\/p>\n<p>At the start of each Sprint<\/p>\n<p>It doesn&#8217;t need to be prioritized<\/p>\n<p>Once at the beginning of the project<\/p>\n<p>Overall explanation<\/p>\n<p>The Product Backlog should be prioritized at the start of each Sprint to support Sprint Planning.<\/p>\n<p>Domain<\/p>\n<p>Product Backlog<\/p>\n<p>Question 64<\/p>\n<p>True or False: The Development Team can modify the Sprint Backlog during the Sprint to add or remove User Stories.<\/p>\n<p>Correct answer<\/p>\n<p>TRUE<\/p>\n<p>FALSE<\/p>\n<p>Overall explanation<\/p>\n<p>The Development Team can modify the Sprint Backlog during the Sprint to add or remove User Stories based on the emerging needs and priorities.<\/p>\n<p>Domain<\/p>\n<p>Development Team<\/p>\n<p>Question 65<\/p>\n<p>During Sprint Planning, the Development Team realizes that the Sprint Goal is too ambitious to be achieved within the time frame. What should they do?<\/p>\n<p>Correct answer<\/p>\n<p>Collaborate with the Product Owner to re-prioritize the User Stories and adjust the Sprint Backlog accordingly<\/p>\n<p>Request the Product Owner to reduce the scope of the Sprint by removing some User Stories<\/p>\n<p>Proceed with the original plan and commit to achieving the ambitious Sprint Goal<\/p>\n<p>Increase the duration of the Sprint to accommodate the additional work required to achieve the Sprint Goal<\/p>\n<p>Overall explanation<\/p>\n<p>The Development Team should collaborate with the Product Owner to re-prioritize the User Stories and adjust the Sprint Backlog accordingly.<\/p>\n<p>Domain<\/p>\n<p>Sprint Planning<\/p>\n<p>Question 66<\/p>\n<p>True or False: The Sprint Review is an opportunity for the Development Team to inspect and adapt their working processes.<\/p>\n<p>TRUE<\/p>\n<p>Correct answer<\/p>\n<p>FALSE<\/p>\n<p>Overall explanation<\/p>\n<p>The main purpose of a sprint review is to inspect the outcome of the sprint, collect feedback from all the stakeholders, and adapt the backlog going forward. When done right, a sprint review can help you create transparency, foster collaboration, and generate valuable insights.<\/p>\n<p>Domain<\/p>\n<p>Sprint Review<\/p>\n<p>Question 67<\/p>\n<p>The Scrum Team wants to implement a new practice to improve their development process. What should they do?<\/p>\n<p>Reject the idea of implementing a new practice and continue with their current process<\/p>\n<p>Request approval from senior management before implementing the new practice<\/p>\n<p>Correct answer<\/p>\n<p>Discuss during the Sprint Retrospective and add it to the Product Backlog.<\/p>\n<p>Implement the new practice immediately and evaluate its impact<\/p>\n<p>Overall explanation<\/p>\n<p>The Scrum Team should discuss it in the Sprint Retrospective as that is the appropriate forum and add it to the Product Backlog.<\/p>\n<p>Domain<\/p>\n<p>Scrum Team<\/p>\n<p>Question 68<\/p>\n<p>What is the recommended maximum length of a Sprint?<\/p>\n<p>Correct answer<\/p>\n<p>4 weeks<\/p>\n<p>1 week<\/p>\n<p>2 weeks<\/p>\n<p>6 weeks<\/p>\n<p>Overall explanation<\/p>\n<p>The recommended maximum length of a Sprint is 4 weeks to maintain focus and adaptability.<\/p>\n<p>Domain<\/p>\n<p>Sprint<\/p>\n<p>Question 69<\/p>\n<p>True or False: The Scrum framework prescribes specific project management methodologies.<\/p>\n<p>Correct answer<\/p>\n<p>FALSE<\/p>\n<p>TRUE<\/p>\n<p>Overall explanation<\/p>\n<p>The Scrum framework does not prescribe specific project management methodologies. It provides a framework for iterative and incremental product development.<\/p>\n<p>Domain<\/p>\n<p>Scrum Framework<\/p>\n<p>Question 70<\/p>\n<p>In a Daily Scrum, a Development Team member mentions that they have completed a task but are still waiting for the necessary review and approval. What should the Scrum Master do?<\/p>\n<p>Inform the Product Owner and ask them to expedite the review and approval process<\/p>\n<p>Ignore the issue and continue with the Daily Scrum meeting<\/p>\n<p>Correct answer<\/p>\n<p>Work with the Development Team to identify and resolve any impediments that are delaying the review and approval process<\/p>\n<p>Assign another team member to review and approve the task<\/p>\n<p>Overall explanation<\/p>\n<p>The Scrum Master should work with the Development Team to identify and resolve any impediments that are delaying the review and approval process.<\/p>\n<p>Domain<\/p>\n<p>Daily Scrum<\/p>\n<p>Question 71<\/p>\n<p>What is the recommended duration of the Sprint Review for a Sprint of two weeks?<\/p>\n<p>30 minutes<\/p>\n<p>Correct answer<\/p>\n<p>2 hours<\/p>\n<p>1 hour<\/p>\n<p>4 hours<\/p>\n<p>Overall explanation<\/p>\n<p>Sprint reviews are limited to a maximum of four hours. The general rule of thumb is to allow one hour for sprint review every one week of sprint length. That means teams should timebox sprint review to two hours for a two-week sprint and four hours for a one-month sprint.<\/p>\n<p>Domain<\/p>\n<p>Sprint Review<\/p>\n<p>Question 72<\/p>\n<p>Who is responsible for managing the progress of work during the Sprint?<\/p>\n<p>Product Owner<\/p>\n<p>Scrum Master<\/p>\n<p>Stakeholders<\/p>\n<p>Correct answer<\/p>\n<p>Development Team<\/p>\n<p>Overall explanation<\/p>\n<p>The Development Team is responsible for managing the progress of work during the Sprint.<\/p>\n<p>Domain<\/p>\n<p>Development Team<\/p>\n<p>Question 73<\/p>\n<p>Which statement best describes the Sprint Review?<\/p>\n<p>A meeting to review and approve changes<\/p>\n<p>A meeting to update the Sprint Backlog<\/p>\n<p>Correct answer<\/p>\n<p>A meeting to inspect the Increment<\/p>\n<p>A meeting to discuss issues and risks<\/p>\n<p>Overall explanation<\/p>\n<p>The Sprint Review is an opportunity to inspect the Increment and adapt the Product Backlog.<\/p>\n<p>Domain<\/p>\n<p>Sprint Review<\/p>\n<p>Question 74<\/p>\n<p>During Sprint Planning, the Development Team realizes that they have insufficient capacity to complete all the selected User Stories. What should they do?<\/p>\n<p>Divide the User Stories among the team members and work individually to complete them<\/p>\n<p>Request additional team members to join the Development Team and increase the capacity<\/p>\n<p>Correct answer<\/p>\n<p>Collaborate with the Product Owner to reprioritize the User Stories and select a subset that fits within the available capacity<\/p>\n<p>Extend the Sprint duration to accommodate all the selected User Stories<\/p>\n<p>Overall explanation<\/p>\n<p>The Development Team should collaborate with the Product Owner to reprioritize the User Stories and select a subset that fits within the available capacity.<\/p>\n<p>Domain<\/p>\n<p>Sprint Planning<\/p>\n<p>Question 75<\/p>\n<p>What is the purpose of the Sprint Goal?<\/p>\n<p>To complete all the Product Backlog items<\/p>\n<p>Correct answer<\/p>\n<p>To guide the Development Team&#8217;s work<\/p>\n<p>To satisfy the stakeholders&#8217; demands<\/p>\n<p>To achieve the Definition of Done<\/p>\n<p>Overall explanation<\/p>\n<p>The Sprint Goal guides the Development Team&#8217;s work and provides focus during the Sprint.<\/p>\n<p>Domain<\/p>\n<p>Sprint Goal<\/p>\n<p>Question 76<\/p>\n<p>Who is responsible for creating the Definition of Done?<\/p>\n<p>Correct answer<\/p>\n<p>Development Team<\/p>\n<p>Product Owner<\/p>\n<p>Stakeholders<\/p>\n<p>Scrum Master<\/p>\n<p>Overall explanation<\/p>\n<p>The Development Team is responsible for creating and maintaining the Definition of Done.<\/p>\n<p>Domain<\/p>\n<p>Definition of Done<\/p>\n<p>Question 77<\/p>\n<p>True or False: The Sprint Retrospective is an opportunity for the stakeholders to review the work completed during the Sprint.<\/p>\n<p>Correct answer<\/p>\n<p>FALSE<\/p>\n<p>TRUE<\/p>\n<p>Overall explanation<\/p>\n<p>The sprint retrospective is a recurring meeting dedicated to discussing what went well and what can be improved in a sprint. It also gives a chance to recover from a sprint and prepare for the next one.<\/p>\n<p>Domain<\/p>\n<p>Sprint Retrospective<\/p>\n<p>Question 78<\/p>\n<p>True or False: The Scrum Master is responsible for assigning tasks to the Development Team members.<\/p>\n<p>Correct answer<\/p>\n<p>FALSE<\/p>\n<p>TRUE<\/p>\n<p>Overall explanation<\/p>\n<p>The Scrum Master is not responsible for assigning tasks to the Development Team members.<\/p>\n<p>Domain<\/p>\n<p>Scrum Master<\/p>\n<p>Question 79<\/p>\n<p>Which statement best describes the Product Owner?<\/p>\n<p>Manages the Development Team<\/p>\n<p>Provides technical expertise<\/p>\n<p>Correct answer<\/p>\n<p>Represents the stakeholders&#8217; interests<\/p>\n<p>Defines the Sprint Goal<\/p>\n<p>Overall explanation<\/p>\n<p>The Product Owner represents the interests of the stakeholders and ensures value is delivered.<\/p>\n<p>Domain<\/p>\n<p>Product Owner<\/p>\n<p>Question 80<\/p>\n<p>What is the purpose of the Sprint Burndown Chart in Scrum?<\/p>\n<p>To track the number of completed Product Backlog items<\/p>\n<p>To estimate the effort required for each Product Backlog item<\/p>\n<p>Correct answer<\/p>\n<p>To visualize the remaining work and progress in the Sprint<\/p>\n<p>To track the team&#8217;s attendance at Scrum events<\/p>\n<p>Overall explanation<\/p>\n<p>The purpose of the Sprint Burndown Chart is to visualize the remaining work and progress in the Sprint, helping the team monitor their progress towards achieving the Sprint Goal.<\/p>\n<p>Domain<\/p>\n<p>Sprint Burndown Chart<\/p>\n","protected":false},"excerpt":{"rendered":"<p>Scrum Master Mock Exam Simulator 2 &#8211; Results Question 1 What is the purpose of the Sprint Retrospective? To update the Product Backlog To discuss upcoming Sprint Backlog items Correct answer To inspect and adapt the Scrum Team To review the work completed in the Sprint Overall explanation The Sprint Retrospective focuses on inspecting and [&hellip;]<\/p>\n","protected":false},"author":1,"featured_media":0,"comment_status":"closed","ping_status":"open","sticky":false,"template":"","format":"standard","meta":{"footnotes":""},"categories":[5],"tags":[],"class_list":["post-26","post","type-post","status-publish","format-standard","hentry","category-psm-i-exam-list"],"_links":{"self":[{"href":"https:\/\/exam.kimson.us\/index.php?rest_route=\/wp\/v2\/posts\/26","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/exam.kimson.us\/index.php?rest_route=\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/exam.kimson.us\/index.php?rest_route=\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/exam.kimson.us\/index.php?rest_route=\/wp\/v2\/users\/1"}],"replies":[{"embeddable":true,"href":"https:\/\/exam.kimson.us\/index.php?rest_route=%2Fwp%2Fv2%2Fcomments&post=26"}],"version-history":[{"count":3,"href":"https:\/\/exam.kimson.us\/index.php?rest_route=\/wp\/v2\/posts\/26\/revisions"}],"predecessor-version":[{"id":205,"href":"https:\/\/exam.kimson.us\/index.php?rest_route=\/wp\/v2\/posts\/26\/revisions\/205"}],"wp:attachment":[{"href":"https:\/\/exam.kimson.us\/index.php?rest_route=%2Fwp%2Fv2%2Fmedia&parent=26"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/exam.kimson.us\/index.php?rest_route=%2Fwp%2Fv2%2Fcategories&post=26"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/exam.kimson.us\/index.php?rest_route=%2Fwp%2Fv2%2Ftags&post=26"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}