Question 49
The Scrum Master notices that the Daily Scrum has become a status report meeting where team members provide lengthy updates. What should the Scrum Master do to address this issue?
Introduce a time-box and enforce shorter individual updates during the Daily Scrum.
Cancel the Daily Scrum and rely on asynchronous communication for updates.
Facilitate the team in understanding the purpose of the Daily Scrum and guide them to focus on the three ##### Questions.
Encourage team members to share blockers and seek assistance during the Daily Scrum.
Overall explanation
In this scenario, the Scrum Master should facilitate the team in understanding the purpose of the Daily Scrum and guide them to focus on the three ##### Questions: What did I do yesterday? What will I do today? Are there any impediments in my way? They can also introduce a time-box to keep individual updates concise.