PSM-I.001.018
January 12, 2025
Question 18
True or False: The Sprint Backlog can only be modified by the Development Team during the Sprint.
TRUE
FALSE
Overall explanation
The Sprint Backlog can be modified throughout the Sprint, but only by the Development Team in collaboration with the Product Owner and under the guidance of the Scrum Master.
Domain
Artifacts