Question 18

True or False: The Sprint Backlog can only be modified by the Development Team during the Sprint.

TRUE

FALSE

Overall explanation

The Sprint Backlog can be modified throughout the Sprint, but only by the Development Team in collaboration with the Product Owner and under the guidance of the Scrum Master.