PSM-I.001.040

Question 40

True or False: The Sprint Backlog is a fixed scope and cannot be adjusted during the Sprint.

FALSE

TRUE

Overall explanation

The Sprint Backlog is not a fixed scope and can be adjusted throughout the Sprint. As the Development Team learns more, new information emerges, or priorities change, they can collaborate with the Product Owner to add, remove, or reorder the items in the Sprint Backlog.

Domain

Artifacts