HomeScrum.orgPSM I[PSM I] Question #001PSM-I.001.005 Scrum Master explains Product Backlog Items to the Developers? 1

PSM-I.001.005 Scrum Master explains Product Backlog Items to the Developers? 1

January 12, 2025
Question 5

Scrum Master explains Product Backlog Items to the Developers?

  • TRUE

  • FALSE

Overall explanation

It is the Product Owner responsible for managing the Product Backlog and explain the items to the Developers.

Domain

Scrum