PSM-I.001.039

Question 39

The Product Owner wants to change the Sprint Goal midway through the Sprint due to shifting market conditions. What should the Scrum Team do in response to this request?

Evaluate the impact of the requested change on the current Sprint Backlog.

Communicate the potential impact to stakeholders and seek their input.

Collaborate with the Product Owner to understand the rationale behind the requested change and assess its impact on the Sprint Goal.

Determine if the change aligns with the Scrum values and principles.

Overall explanation

In this scenario, the Scrum Team should collaborate with the Product Owner to understand the rationale behind the requested change and assess its impact on the Sprint Goal. They should determine if the change aligns with the Scrum values and principles. Communicating the potential impact to stakeholders and seeking their input can help make informed decisions.

Domain

Scrum