PSM-I.001.032
Question 32
A Development Team member raises concerns about the clarity and detailed requirements of a Product Backlog item during the Sprint. What should they do?
Proceed with the implementation based on the current understanding and assumptions.
Highlight it to the Development team in the Daily Scrum
Ignore the concerns and focus on completing other items in the Sprint Backlog.
Collaborate with the Product Owner to gain a better understanding of the item and refine its details.
Overall explanation
In this scenario, the Development Team should collaborate with the Product Owner to gain a better understanding of the unclear Product Backlog item and refine its details. They can seek clarification and work together to ensure a shared understanding of the item’s requirements. Also, the team member should highlight it in the Daily Scrum.
Domain
Scrum