PSM-I.001.055

Question 55

True or False: The Scrum Master is responsible for measuring the velocity of the Development Team.

FALSE

TRUE

Overall explanation

The Development Team is responsible for measuring its own velocity, which represents the amount of work it can complete in a Sprint. The Scrum Master may help facilitate the measurement process but is not directly responsible for it.

Domain

Roles