The Scrum Master observes that the Development Team is struggling with estimation accuracy, leading to frequent scope changes during the Sprint. What should the Scrum Master do to address this issue?

Increase the time allocated for Sprint Planning to allow for more detailed estimation.

Conduct training or workshops to enhance the Development Team’s estimation skills.

Facilitate a discussion to explore alternative estimation techniques and encourage the use of relative sizing.

Collaborate with the Product Owner to provide clearer requirements and acceptance criteria.

Overall explanation

In this scenario, the Scrum Master should facilitate a discussion with the Development Team to explore alternative estimation techniques, such as relative sizing. They should also collaborate with the Product Owner to provide clearer requirements and acceptance criteria to improve estimation accuracy.

Domain

Scrum