PSM-I.001.022 During the Sprint Review, stakeholders provide feedback on a recently delivered Increment

Question 22

During the Sprint Review, stakeholders provide feedback on a recently delivered Increment. They express concerns about the user interface design and suggest improvements. What should the Scrum Team do with this feedback?

Assess the feasibility and impact of the suggested improvements.

Collaborate with the Product Owner to prioritize the feedback and incorporate relevant improvements in the Product Backlog.

Adapt the Definition of Done to include specific criteria for user interface design.

Discuss the feedback with the stakeholders to gain a deeper understanding of their concerns.

Overall explanation

In this scenario, the Scrum Team should discuss the feedback with the stakeholders to gain a deeper understanding of their concerns. They should assess the feasibility and impact of the suggested improvements and collaborate with the Product Owner to prioritize and incorporate relevant improvements in the Product Backlog.