PSM-I.001.026

Question 26

True or False: The Product Owner can add new items or modify existing items in the Sprint Backlog during the Sprint to adapt to changing requirements.

FALSE

TRUE

Overall explanation

Developers can change the Sprint Backlog. Sprint Backlog is planed by Developers and define the work necessary to create an Increment that meets the Definition of Done. Developers change the Sprint Backlog after consulting with Product Owner.

Domain

Artifacts