PSM-I.005 Scrum Master Mock Exam Simulator 5
Scrum Master Mock Exam Simulator 5 – Results
Back to result overview
Attempt 1
All domains
- 80 all
- 0 correct
- 0 incorrect
- 80
- 0 marked
Collapse all questions
Question 1
Who is responsible for updating the progress of the work completed and remaining during a Sprint?
Product Owner
Scrum Master
Correct answer
Development Team
Stakeholders
Overall explanation
The Development Team is responsible for updating the progress of the work during a Sprint.
Domain
Development Team
Question 2
During a Daily Scrum, a Development Team member realizes that they are working on the wrong task. What should they do?
Continue working on the wrong task and fix it later
Correct answer
Share the issue with the rest of the Development Team and switch to the correct task
Inform the Product Owner about the issue and ask for guidance
Request the Scrum Master to reassign the tasks for all the Development Team members
Overall explanation
The Development Team member should share the issue with the rest of the Development Team and switch to the correct task.
Domain
Daily Scrum
Question 3
The Development Team is experiencing technical difficulties that may impact the Sprint Goal. What should they do?
Escalate the technical difficulties to senior management for resolution
Inform the Product Owner about the technical difficulties and seek their guidance
Continue working and hope that the technical difficulties will be resolved
Correct answer
Collaborate with the Scrum Master to find a solution and minimize the impact
Overall explanation
The Development Team should collaborate with the Scrum Master to find a solution and minimize the impact.
Domain
Development Team
Question 4
True or False: The Sprint Review is an opportunity for the Development Team to inspect the Increment and make changes to the Sprint Backlog.
Correct answer
FALSE
TRUE
Overall explanation
The Sprint Review is an opportunity for the Scrum Team to inspect the Increment, not make changes to the Sprint Backlog.
Domain
Sprint Review
Question 5
What is the recommended time-box for the Sprint Planning event for a two-weeks Sprint.
Correct answer
4 hours
1 hour
2 hours
8 hours
Overall explanation
The recommended time-box for the Sprint Planning event for a two-weeks Sprint is 4 hours.
Domain
Sprint Planning
Question 6
During a Sprint, the Development Team identifies a risk that may impact the Sprint Goal. What should they do?
Escalate the risk to senior management for resolution
Correct answer
Collaborate with the Product Owner to assess the risk and take necessary actions
Inform the Scrum Master about the risk and let them handle it
Ignore the risk and hope that it doesn’t impact the Sprint Goal
Overall explanation
The Development Team should collaborate with the Product Owner to assess the risk and take necessary actions.
Domain
Development Team
Question 7
True or False: The Product Owner is responsible for prioritizing the Product Backlog and deciding the order of User Stories to be worked on.
Correct answer
TRUE
FALSE
Overall explanation
The Product Owner is responsible for prioritizing the Product Backlog and deciding the order of User Stories to be worked on.
Domain
Product Owner
Question 8
The Scrum Master is not allowed to act as a Developer.
Correct answer
FALSE
TRUE
Overall explanation
The Scrum Master can act as a Developer. Scrum doesn’t prohibits it but also, doesn’t encourage or recommend it either.
Domain
Scrum Master
Question 9
Select the correct Scrum Pillars.
Dedication
Correct selection
Transparency
Focus
Correct selection
Inspection
Overall explanation
The three pillars of Scrum are Transparency, Inspection, and Adaptation.
Domain
Scrum Pillars
Question 10
True or False: The Product Owner is responsible for creating and maintaining the Sprint Backlog.
Correct answer
FALSE
TRUE
Overall explanation
The Product Owner is responsible for creating and maintaining the Product Backlog, not the Sprint Backlog.
Domain
Product Backlog
Question 11
True or False: The Sprint Retrospective is an opportunity to inspect and adapt the Scrum Team’s interactions and practices.
FALSE
Correct answer
TRUE
Overall explanation
The Sprint Retrospective is an opportunity to inspect and adapt the Scrum Team’s interactions and practices.
Domain
Sprint Retrospective
Question 12
What is the recommended size for a Scrum Development Team when the team is working remotely.
2 – 8 members
5-7 members
10-15 members
Correct answer
3-9 members
Overall explanation
The recommended size for a Scrum Development Team is 3-9 members.
Domain
Scrum Development Team
Question 13
In Scrum, what is the primary responsibility of the Development Team?
To manage the project
Correct answer
To deliver a potentially releasable Increment
To prioritize the Product Backlog
To define the product features
Overall explanation
The primary responsibility of the Development Team is to deliver a potentially releasable Increment at the end of each Sprint.
Domain
Development Team
Question 14
The Development Team has concerns about the quality of the Increment due to time constraints. What should they do?
Correct answer
Collaborate with the Product Owner to reprioritize and adjust the Sprint Backlog
Sacrifice additional features to ensure the quality of the Increment
Request additional time from the stakeholders to improve the quality of the Increment
Ignore the quality concerns and deliver the Increment on time
Overall explanation
The Development Team should collaborate with the Product Owner to reprioritize and adjust the Sprint Backlog.
Domain
Development Team
Question 15
True or False: The Scrum Master is responsible for making all the decisions related to the Sprint and the Development Team.
TRUE
Correct answer
FALSE
Overall explanation
The Scrum Master is not responsible for making all the decisions. It is a collaborative effort within the Scrum Team.
Domain
Scrum Master
Question 16
What is the purpose of the Daily Scrum?
To provide a status update
Correct answer
To synchronize activities
To discuss and resolve issues
To review and approve user stories
Overall explanation
The Daily Scrum helps synchronize activities and create a plan for the next 24 hours.
Domain
Daily Scrum
Question 17
What is the maximum duration for a Sprint for a business new to Scrum.
2 weeks
1 week
Correct answer
4 weeks
6 weeks
Overall explanation
The maximum duration for a Sprint is 4 weeks regardless of if a business is new to Scrum or not.
Domain
Sprint
Question 18
The Product Owner wants to remove an item from the Product Backlog permanently. What should they do?
Correct answer
Collaborate with the stakeholders and assess the impact of removing the item from the Product Backlog
Reject the Product Owner’s request and keep the item in the Product Backlog
Remove the item from the Product Backlog without any discussion
Request the Scrum Master to make the decision on whether to remove the item from the Product Backlog
Overall explanation
The Product Owner should collaborate with the stakeholders and assess the impact of removing the item from the Product Backlog.
Domain
Product Owner
Question 19
True or False: The Scrum Master is responsible for ensuring that the Development Team meets the Sprint Goal.
TRUE
Correct answer
FALSE
Overall explanation
The Scrum Master is not responsible for ensuring that the Development Team meets the Sprint Goal. It is a collective responsibility.
Domain
Scrum Master
Question 20
During a Sprint, the Product Owner identifies a critical defect in the Increment that requires immediate attention. What should they do?
Request the Scrum Master to address the defect immediately
Correct answer
Collaborate with the Development Team to determine the impact on the Sprint Goal and prioritize accordingly
Ignore the defect and continue with the planned User Stories
Notify the stakeholders about the defect and seek their guidance
Overall explanation
The Product Owner should collaborate with the Development Team to determine the impact on the Sprint Goal and prioritize accordingly.
Domain
Product Owner
Question 21
The Scrum Master realizes that the Development Team is not adhering to the agreed Scrum practices. What should they do?
Correct answer
Facilitate a retrospective to identify the reasons for non-adherence and discuss potential improvements
Request the Product Owner to enforce the adherence to Scrum practices
Ignore the issue and hope that the Development Team will self correct
Punish the Development Team for not following the Scrum practices
Overall explanation
The Scrum Master should facilitate a retrospective to identify the reasons for non-adherence and discuss potential improvements.
Domain
Scrum Master
Question 22
Which event serves as an opportunity for Stakeholders to inspect the Increment and provide feedback?
Daily Scrum
Sprint Retrospective
Sprint Planning
Correct answer
Sprint Review
Overall explanation
The Sprint Review is where the stakeholders inspects the Increment and provides feedback.
Domain
Sprint Review
Question 23
During a Sprint, the Development Team realizes that the selected User Stories are not feasible within the given time frame. What should they do?
Continue working on the selected User Stories and extend the Sprint duration
Request additional team members to complete the selected User Stories
Correct answer
Collaborate with the Product Owner to reprioritize and adjust the Sprint Backlog
Drop the selected User Stories and focus on the remaining ones
Overall explanation
The Development Team should collaborate with the Product Owner to reprioritize and adjust the Sprint Backlog.
Domain
Development Team
Question 24
Which event is used to review and adjust the Sprint Backlog?
Sprint Retrospective
Correct answer
Sprint Planning
Daily Scrum
Sprint Review
Overall explanation
The Sprint Planning event is used to review and adjust the Sprint Backlog for the upcoming Sprint.
Domain
Sprint Planning
Question 25
The Product Owner wants to change the Sprint Goal in the middle of the Sprint due to new market opportunities. What should the Development Team do?
Immediately change the Sprint Goal without any discussion
Request the Scrum Master to make the decision on whether to change the Sprint Goal
Reject the Product Owner’s request and continue working on the original Sprint Goal
Correct answer
Collaborate with the Development Team to assess the impact on the selected User Stories and the Sprint Goal
Overall explanation
The Product Owner should collaborate with the Development Team to assess the impact on the selected User Stories and the Sprint Goal.
Domain
Development Team
Question 26
True or False: The Sprint Retrospective is a formal meeting where the Development Team presents their work to the stakeholders.
TRUE
Correct answer
FALSE
Overall explanation
The Sprint Retrospective is a meeting within the Scrum Team to inspect and adapt their working processes, not a formal presentation to stakeholders.
Domain
Sprint Retrospective
Question 27
The Development Team wants to change the Sprint duration for future Sprints to have more time for development. What should they do?
Correct answer
Discuss this is in the Sprint Retrospective event.
Reject the idea of changing the Sprint duration and continue with the current duration
Request approval from senior management before changing the Sprint duration
Extend the Sprint duration without involving the Product Owner and the Scrum Master
Overall explanation
The Development Team should collaborate with the Product Owner and the Scrum Master to assess and discuss it in detail at the Sprint Retrospective.
Domain
Development Team
Question 28
True or False: The Scrum Master is responsible for removing any impediments that the Development Team encounters during the Sprint.
FALSE
Correct answer
TRUE
Overall explanation
The Scrum Master is responsible for removing any impediments that the Development Team encounters during the Sprint.
Domain
Scrum Master
Question 29
What is the recommended maximum size for a Development Team?
Correct answer
9 members
7 members
5 members
There is no recommended maximum size
Overall explanation
The recommended maximum size for a Development Team is 9 members to promote effective collaboration and communication.
Domain
Development Team
Question 30
The Scrum Master identifies a conflict between two Development Team members during the Sprint. What should they do?
Remove one of the members from the Development Team
Request the Product Owner to mediate and resolve the conflict
Correct answer
Facilitate a conversation between the two members to address the conflict and find a resolution
Ignore the conflict and let the Development Team members resolve it on their own
Overall explanation
The Scrum Master should facilitate a conversation between the two
Question 31
True or False: The Sprint Review is an opportunity for the Product Owner to present the Increment to the stakeholders.
FALSE
Correct answer
TRUE
Overall explanation
The Sprint Review is an opportunity for the Scrum Team to present the Increment to the stakeholders.
Domain
Sprint Review
Question 32
True or False: The Scrum Master is responsible for updating the Burndown Chart and tracking the progress of the Sprint.
Correct answer
FALSE
TRUE
Overall explanation
The Development Team is responsible for updating the Burndown Chart and tracking the progress of the Sprint.
Domain
Scrum Master
Question 33
True or False: The Sprint Review is an opportunity for the stakeholders to provide feedback on the Increment and make changes to the Product Backlog.
Correct answer
FALSE
TRUE
Overall explanation
The Sprint Review is an opportunity for the stakeholders to provide feedback on the Increment, not make changes to the Product Backlog.
Domain
Sprint Review
Question 34
True or False: The Product Owner is responsible for managing the team’s progress during the Sprint and ensuring that the tasks are completed on time.
TRUE
Correct answer
FALSE
Overall explanation
The Development Team is responsible for managing the team’s progress during the Sprint and ensuring that the tasks are completed on time.
Domain
Product Owner
Question 35
What is the purpose of the Daily Scrum?
Correct answer
To synchronize activities
To discuss and resolve issues
To provide a status update
To review and approve user stories
Overall explanation
The Daily Scrum helps synchronize activities and create a plan for the next 24 hours.
Domain
Daily Scrum
Question 36
True or False: The Scrum Master is responsible for creating and maintaining the Product Backlog.
TRUE
Correct answer
FALSE
Overall explanation
The Product Owner is responsible for creating and maintaining the Product Backlog, not the Scrum Master.
Domain
Product Backlog
Question 37
What is the recommended maximum length for a Sprint?
Correct answer
4 weeks
It can vary depending on the nature of the project
2 weeks
1 week
Overall explanation
The recommended maximum length for a Sprint is 4 weeks to maintain a sustainable pace and enable frequent inspection and adaptation.
Domain
Sprint
Question 38
What is the recommended size for a Scrum Development Team comprising 3 highly experienced developers.
10-15 members
Correct answer
3-9 members
5-7 members
3-10 members
Overall explanation
The recommended size for a Scrum Development Team is 3-9 members.
Domain
Scrum Development Team
Question 39
Which event is used to inspect the Increment and adapt the Product Backlog if needed?
Daily Scrum
Sprint Planning
Correct answer
Sprint Review
Sprint Retrospective
Overall explanation
The Sprint Review is where the Increment is inspected, and the Product Backlog may be adapted.
Domain
Sprint Review
Question 40
What is the recommended frequency for updating the Sprint Backlog during a Sprint?
It can vary depending on the team’s needs
Weekly
Correct answer
Daily
Every other day
Overall explanation
The Sprint Backlog should be updated daily to reflect the progress and any changes during the Sprint.
Domain
Sprint Backlog
Question 41
What is the purpose of the Sprint Burndown Chart?
Correct answer
To track the progress of work
To visualize the Product Backlog
To calculate team velocity
To estimate effort for user stories
Overall explanation
The Sprint Burndown Chart helps track the progress of work and shows the remaining work throughout the Sprint.
Domain
Sprint Burndown Chart
Question 42
The Development Team is facing challenges in understanding the requirements for a User Story. What should they do?
Request the Scrum Master to communicate the requirements clearly
Make assumptions and proceed with the development
Correct answer
Collaborate with the Product Owner to clarify the requirements
Ignore the challenges and continue working based on their interpretation
Overall explanation
The Development Team should collaborate with the Product Owner to clarify the requirements.
Domain
Development Team
Question 43
Who has the authority to cancel a Sprint?
Stakeholders
Scrum Master
Correct answer
Product Owner
Development Team
Overall explanation
The Product Owner has the authority to cancel a Sprint if the Sprint Goal becomes obsolete.
Domain
Product Owner
Question 44
True or False: The Product Owner is responsible for facilitating the Daily Scrum meeting and ensuring that the Development Team members attend.
Correct answer
FALSE
TRUE
Overall explanation
The Product Owner is not responsible for facilitating the Daily Scrum meeting. It is the responsibility of the Development Team.
Domain
Product Owner
Question 45
True or False: The Sprint Retrospective is a mandatory event in Scrum and must be conducted at the end of each Sprint.
Correct answer
TRUE
FALSE
Overall explanation
The Sprint Retrospective is a mandatory event in Scrum and must be conducted at the end of each Sprint.
Domain
Sprint Retrospective
Question 46
Who is responsible for the Product Backlog in Scrum when the Product Owner is also a Developer.
Scrum Master
Development Team
Stakeholders
Correct answer
Product Owner
Overall explanation
The Product Owner is responsible for the Product Backlog.
Domain
Product Backlog
Question 47
The Product Owner wants to add more User Stories to the Sprint Backlog during the Sprint. What should the Scrum Master do?
Reject the Product Owner’s request to add more User Stories
Make the decision to add more User Stories on behalf of the Development Team
Allow the Product Owner to add the User Stories without any discussion
Correct answer
Facilitate a discussion with the Product Owner and the Development Team to assess the impact on the Sprint Goal
Overall explanation
The Scrum Master should facilitate a discussion with the Product Owner and the Development Team to assess the impact on the Sprint Goal.
Domain
Scrum Master
Question 48
Which event serves as an opportunity for the Product Owner to inspect the Increment and provide feedback?
Sprint Planning
Sprint Retrospective
Correct answer
Sprint Review
Daily Scrum
Overall explanation
The Sprint Review is where the Product Owner inspects the Increment and provides feedback.
Domain
Sprint Review
Question 49
The Development Team wants to change their Definition of Done to include additional criteria. What should they do?
Request external consultants to decide on the changes to the Definition of Done
Reject the idea of changing the Definition of Done and continue with the current criteria
Correct answer
Collaborate with the Product Owner and the Scrum Master to assess the impact of the changes
Implement the changes to the Definition of Done without involving the Product Owner and the Scrum Master
Overall explanation
The Development Team should collaborate with the Product Owner and the Scrum Master to assess the impact of the changes.
Domain
Development Team
Question 50
True or False: The Scrum Master is responsible for removing impediments that are blocking the progress of the Development Team.
FALSE
Correct answer
TRUE
Overall explanation
The Scrum Master has the responsibility to identify and remove impediments to help the Development Team progress.
Domain
Scrum Master
Question 51
In Scrum, who is responsible for the order of items in the Product Backlog?
Stakeholders
Correct answer
Product Owner
Scrum Master
Development Team
Overall explanation
The Product Owner is responsible for prioritizing and ordering the items in the Product Backlog.
Domain
Product Backlog
Question 52
True or False: The Sprint Retrospective is an opportunity to inspect the Increment and adapt the Product Backlog accordingly.
TRUE
Correct answer
FALSE
Overall explanation
The Sprint Retrospective is an opportunity to inspect the Sprint and adapt the working processes, not the Product Backlog.
Domain
Sprint Retrospective
Question 53
The Scrum Master and Product Owner roles can also be Developers within the Scrum Team.
Correct answer
FALSE
TRUE
Overall explanation
Yes the Product Owner and Scrum Master roles can be Developers. Not prohibited by Scrum but not recommended either.
Domain
Scrum Roles
Question 54
During a Sprint, the Product Owner identifies a valuable User Story that was not planned for the current Sprint. What should they do?
Request the Scrum Master to make the decision on whether to add the User Story
Add the User Story to the current Sprint without considering the impact
Reject the User Story and continue with the planned User Stories
Correct answer
Add the User Story to the Product Backlog and consider it for future Sprints
Overall explanation
The Product Owner should add the User Story to the Product Backlog and consider it for future Sprints.
Domain
Product Owner
Question 55
Who is responsible for ensuring transparency in the Scrum Team’s progress toward the Sprint Goal?
Development Team
Correct answer
Scrum Master
Product Owner
Stakeholders
Overall explanation
The Scrum Master is responsible for ensuring transparency in the Scrum Team’s progress toward the Sprint Goal.
Domain
Scrum Master
Question 56
True or False: The Scrum Master is a management position within the organization.
Correct answer
FALSE
TRUE
Overall explanation
The Scrum Master is not a management position, but a facilitative role within the organization for promotion of Scrum and provide coaching to the team that the role serves.
Domain
Scrum Master
Question 57
A Product Owner can also be a Developer.
FALSE
Correct answer
TRUE
Overall explanation
Yes the Product Owner can be a Developer. Not prohibited by Scrum but not recommended either.
Domain
Product Owner
Question 58
In Scrum, who is responsible for ensuring the Development Team understands the Product Goal and the upcoming work in the Product Backlog?
Correct answer
Product Owner
Stakeholders
Development Team
Scrum Master
Overall explanation
The Product Owner is responsible for ensuring the Development Team understands the Product Goal and the upcoming work.
Domain
Product Owner
Question 59
During a Daily Scrum, a Development Team member realizes that they won’t be able to complete their assigned task. What should they do?
Inform the Product Owner about the issue and ask for a different task
Hide the issue and hope that someone else will complete the task
Request the Scrum Master to reassign the task to another Development Team member
Correct answer
Share the issue with the rest of the Development Team and discuss possible solutions
Overall explanation
The Development Team member should share the issue with the rest of the Development Team and discuss possible solutions.
Domain
Daily Scrum
Question 60
What is the recommended frequency for conducting Sprint Retrospectives?
Correct answer
Every Sprint
Once per month
Once per quarter
Every other Sprint
Overall explanation
Sprint Retrospectives should be conducted at the end of every Sprint.
Domain
Sprint Retrospective
Question 61
True or False: The Product Owner is a member of the Development Team.
TRUE
Correct answer
FALSE
Overall explanation
The Product Owner is not a member of the Development Team but works closely with them to prioritize and clarify requirements.
Domain
Product Owner
Question 62
True or False: The Product Owner can change the Sprint Goal during the Sprint.
Correct answer
FALSE
TRUE
Overall explanation
Once the Sprint has started, the Sprint Goal should remain unchanged to provide a clear focus for the Development Team.
Domain
Sprint Goal
Question 63
What is the role of the Scrum Master in the Daily Scrum?
Correct answer
To facilitate the meeting
To provide status updates
To make decisions for the team
To assign tasks to the team
Overall explanation
The Scrum Master’s role in the Daily Scrum is to facilitate the meeting and ensure it stays focused.
Domain
Scrum Master
Question 64
Which artifact captures the commitment of the Development Team for the upcoming Sprint?
Product Backlog
Product Increment
Burndown Chart
Correct answer
Sprint Backlog
Overall explanation
The Sprint Backlog captures the commitment of the Development Team for the upcoming Sprint.
Domain
Sprint Backlog
Question 65
True or False: The Scrum Master ensures that the Development Team has a clear understanding of the selected Product Backlog items.
TRUE
Correct answer
FALSE
Overall explanation
The Scrum Master is not responsible for ensuring the Development Team’s understanding of selected Product Backlog items.
Domain
Scrum Master
Question 66
Who is responsible for managing the progress of work during a Sprint?
Product Owner
Scrum Master
Project Manager
Correct answer
Development Team
Overall explanation
The Development Team is responsible for managing the progress of work during a Sprint.
Domain
Development Team
Question 67
During a Sprint, the Development Team realizes that they need to acquire new skills to complete the User Stories. What should they do?
Continue working on the User Stories and hope that they can learn the required skills as they progress
Request external training for the required skills
Reject the User Stories that require new skills and focus on the ones they are familiar with
Correct answer
Collaborate with the Product Owner to adjust the Sprint Backlog and acquire the necessary skills
Overall explanation
The Development Team should collaborate with the Product Owner to adjust the Sprint Backlog and acquire the necessary skills.
Domain
Development Team
Question 68
True or False: The Product Owner role can be shared among multiple individuals.
Correct answer
FALSE
TRUE
Overall explanation
The Product Owner role should ideally be fulfilled by one person to ensure accountability and clear decision-making.
Domain
Product Owner
Question 69
The Development Team wants to change the Sprint Backlog during the Sprint to reflect new insights. What should they do?
Ask the Scrum Master to decide whether to change the Sprint Backlog
Reject the idea of changing the Sprint Backlog and continue with the original plan
Correct answer
Collaborate with the Product Owner to adjust the Sprint Backlog based on the new insights
Continue working on the existing Sprint Backlog without any changes
Overall explanation
The Development Team should collaborate with the Product Owner to adjust the Sprint Backlog based on the new insights.
Domain
Development Team
Question 70
True or False: The Development Team is responsible for determining how much work can be completed in a Sprint.
Correct answer
TRUE
FALSE
Overall explanation
The Development Team is responsible for determining how much work they can commit to delivering in a Sprint.
Domain
Development Team
Question 71
True or False: The Scrum Master is a management position within the Scrum Team
TRUE
Correct answer
FALSE
Overall explanation
The Scrum Master is not a management position, but a facilitative role within the Scrum Team.
Domain
Scrum Master
Question 72
What is the purpose of the Sprint Goal?
To estimate effort for user stories
To outline the tasks for the Sprint
To define the length of the Sprint
Correct answer
To provide a high-level vision
Overall explanation
The Sprint Goal provides a high-level vision for the Sprint, guiding the Development Team’s work.
Domain
Sprint Goal
Question 73
What is the maximum time-box for the Sprint Review?
2 hours
Correct answer
4 hours
30 minutes
1 hour
Overall explanation
The maximum time-box for the Sprint Review is 4 hours.
Domain
Sprint Review
Question 74
The Product Owner wants to remove a User Story from the Sprint Backlog during the Sprint. What should the Development Team do?
Refuse the Product Owner’s request and continue working on the User Story
Remove the User Story without considering the impact on the Sprint Goal
Correct answer
Collaborate with the Product Owner to assess the impact of removing the User Story on the Sprint Goal
Request approval from senior management before removing the User Story
Overall explanation
The Development Team should collaborate with the Product Owner to assess the impact of removing the User Story on the Sprint Goal.
Domain
Development Team
Question 75
Who is responsible for managing the progress of work during a Sprint?
Scrum Master
Product Owner
Project Manager
Correct answer
Development Team
Overall explanation
The Development Team is responsible for managing the progress of work during a Sprint.
Domain
Development Team
Question 76
The Development Team estimates the User Stories during Sprint Planning but realizes later that the estimates were inaccurate. What should they do?
Continue working on the User Stories without considering the accuracy of the estimates
Correct answer
Reflect on the reasons for inaccurate estimates and improve their estimation process
Request additional time to complete the User Stories due to inaccurate estimates
Ask the organization for more resources to complete the work
Overall explanation
The Development Team should reflect on the reasons for inaccurate estimates and improve their estimation process.
Domain
Development Team
Question 77
The Development Team cant depend on external resources for their work.
FALSE
Correct answer
TRUE
Overall explanation
This is correct as this is against the spirit of a cross-functional team.
Domain
Development Team
Question 78
The Scrum Team is required to release an increment at the Sprint.
Correct answer
FALSE
TRUE
Overall explanation
The is not correct. Releasing the increment is not mandatory.
Domain
Sprint
Question 79
Who is responsible for the Product Backlog in Scrum?
Scrum Master
Correct answer
Product Owner
Stakeholders
Development Team
Overall explanation
The Product Owner is responsible for the Product Backlog.
Domain
Product Backlog
Question 80
True or False: The Scrum Master is responsible for ensuring that the Daily Scrum meeting is conducted and that the Development Team members attend.
Correct answer
TRUE
FALSE
Overall explanation
The Scrum Master is responsible for ensuring that the Daily Scrum meeting is conducted and that the Development Team members attend.
Domain
Scrum Master