PSM-I.006 Scrum Master Mock Exam Simulator 6

Scrum Master Mock Exam Simulator 6 – Results

Back to result overview

Attempt 1

All domains

  • 80 all
  • 0 correct
  • 0 incorrect
  • 80
  • 0 marked

Collapse all questions

Question 1

Who is responsible for ensuring that the Development Team understands and works towards the Sprint Goal?

Scrum Master

Stakeholders

Product Owner

Correct answer

Development Team

Overall explanation

The Development Team is responsible for understanding and working towards the Sprint Goal as a collective effort.

Domain

Development Team

Question 2

Select the correct Scrum Pillars.

Focus

Correct selection

Transparency

Correct selection

Adaptation

Correct selection

Inspection

Overall explanation

The three pillars of Scrum are Transparency, Inspection, and Adaptation.

Domain

Scrum Pillars

Question 3

Is Examination a Scrum Pillar.

Correct answer

FALSE

TRUE

Overall explanation

The three pillars of Scrum are Transparency, Inspection, and Adaptation.

Domain

Scrum Pillars

Question 4

Scrum is founded on Empiricism and Lean Thinking.

Correct answer

TRUE

FALSE

Overall explanation

According to Scrum Guide: “Scrum is founded on empiricism and lean thinking. Empiricism asserts that knowledge comes from experience and making decisions based on what is observed. Lean thinking reduces waste and focuses on the essentials.”

Domain

Scrum

Question 5

True or False: The Scrum Master and Product Owner are jointly responsible for prioritizing the Product Backlog.

TRUE

Correct answer

FALSE

Overall explanation

The Product Owner is only responsible for prioritizing the Product Backlog based on value and stakeholder needs.

Domain

Product Owner

Question 6

What is the recommended maximum duration for a Sprint Review?

Correct answer

2 hours

8 hours

1 hour

4 hours

Overall explanation

The recommended maximum duration for a Sprint Review is 2 hours for a one-month Sprint, allowing sufficient time for feedback and collaboration.

Domain

Sprint Review

Question 7

Select all the Scrum events that are formal opportunities to inspect and adapt.

Correct selection

Sprint Retrospective

Correct selection

Sprint Planning

Correct selection

Sprint Review

Correct selection

Daily Scrum

Overall explanation

Every event in Scrum is a formal opportunity to inspect and adapt Scrum artifacts.

Domain

Scrum Events

Question 8

The Daily Scrum is underway, and one Development Team member is struggling with a task and needs assistance. What should they do?

All of the above

Correct answer

Share the challenge with the Development Team

Ask for help from the Scrum Master

Assign the task to another team member

Overall explanation

The Development Team member should share the challenge with the Development Team, promoting collaboration and collective problem-solving.

Domain

Daily Scrum

Question 9

During the Sprint Review, stakeholders provide feedback on the completed Increment. Some feedback requires major changes to the product. What should the Product Owner do?

Accept the feedback and immediately incorporate the changes

Disregard the feedback

Prioritize the feedback and plan for future iterations

Correct answer

Discuss the feedback with the stakeholders and determine the appropriate course of action

Overall explanation

The Product Owner should discuss the feedback with the stakeholders and determine the appropriate course of action, considering the impact on the product and its alignment with the overall product vision.

Domain

Sprint Review

Question 10

Scrum Master and Product Owner are jointly responsible for ordering the items in the Product Backlog?

Correct answer

FALSE

TRUE

Overall explanation

Only the Product Owner is responsible for ordering the items in the Product Backlog based on their value and priorities.

Domain

Product Owner

Question 11

During the Sprint, a new requirement emerges from stakeholders that is not in the Sprint Backlog. How should the Development Team handle this situation?

Assess the impact and negotiate with stakeholders

Correct answer

Ignore the new requirement and continue with the current Sprint

Request the Scrum Master to handle the situation

Add the new requirement to the current Sprint Backlog

Overall explanation

The Development Team should continue with their current work and let the Product Owner handle the Stakeholders.

Domain

Sprint Execution

Question 12

What is the primary purpose of the Sprint Review?

To gather feedback from management

Correct answer

To review the completed work and gather feedback from stakeholders

To inspect and adapt the process

To review the completed work and how the team performed

Overall explanation

The primary purpose of the Sprint Review is to demonstrate the Increment and gather feedback from stakeholders for future adaptations.

Domain

Sprint Review

Question 13

True or False: The Product Owner is responsible for estimating the effort required for Product Backlog items.

Correct answer

FALSE

TRUE

Overall explanation

The Development Team is responsible for estimating the effort required for Product Backlog items during Sprint Planning.

Domain

Development Team

Question 14

True or False: The Scrum Master is responsible for managing the Product Backlog.

TRUE

Correct answer

FALSE

Overall explanation

The Product Owner is responsible for managing the Product Backlog, including prioritization and refinement.

Domain

Product Owner

Question 15

Inspection is a Scrum Pillar.

Correct answer

TRUE

FALSE

Overall explanation

The three pillars of Scrum are Transparency, Inspection, and Adaptation.

Domain

Scrum Pillars

Question 16

Sprint Retrospective can be if team does not have time.

Correct answer

FALSE

TRUE

Overall explanation

This is a mandatory Scrum event with the primary purpose to inspect and adapt the process, identifying improvements for the next Sprint.

Domain

Sprint Retrospective

Question 17

What is the recommended maximum duration for a Daily Scrum?

Correct answer

15 minutes

1 hour

30 minutes

45 minutes

Overall explanation

The recommended maximum duration for a Daily Scrum is 15 minutes to keep the meeting focused and efficient.

Domain

Daily Scrum

Question 18

How frequently should be inspection be performed in Scrum.

As frequently as the Product Owner decides

Correct answer

As much frequently as possible

As frequently as the Scrum Master decides

As frequently as the Management decides

Overall explanation

Scrum suggests that the artifacts and progress towards agreed goals should be inspected frequently

Domain

Scrum

Question 19

True or False: The Development Team is responsible for defining the acceptance criteria for Product Backlog items.

FALSE

Correct answer

TRUE

Overall explanation

The Development Team is responsible for defining the acceptance criteria as part of their collaboration with the Product Owner.

Domain

Development Team

Question 20

What is the recommended frequency for conducting the Sprint Retrospective?

Correct answer

After every Sprint

Once a month

Once a year

After every other Sprint

Overall explanation

The Sprint Retrospective should be conducted after every Sprint to enable continuous improvement.

Domain

Sprint Retrospective

Question 21

What is the recommended timebox for the Daily Scrum when the team is remote

Correct answer

15 minutes

45 minutes

30 minutes

1 hour

Overall explanation

The recommended timebox for the Daily Scrum is 15 minutes to keep the meeting focused and efficient.

Domain

Daily Scrum

Question 22

If multiple Scrum teams are working on a product, there would be multiple Product Owners.

Correct answer

FALSE

TRUE

Overall explanation

There would always be one Product Backlog and Product Owner for a product even when multiple teams are working on the Product.

Domain

Sprint Retrospective

Question 23

Sprint Review event is for creating a joint execution plan with project stakeholders.

Correct answer

FALSE

TRUE

Overall explanation

The purpose of the Sprint Review event is to review the completed work and gather feedback from stakeholders to adapt the Product Backlog.

Domain

Sprint Review

Question 24

The Product Owner identifies a critical bug in the product that needs immediate attention. What should the Product Owner do?

Immediately interrupt the Sprint to address the bug

Assign the bug to the Scrum Master

Correct answer

Add the bug to the Product Backlog for future prioritization

Inform the Development Team during the Daily Scrum

Overall explanation

The Product Owner should add the critical bug to the Product Backlog for future prioritization and discuss it with the Development Team during Sprint Planning to plan its resolution in a future Sprint.

Domain

Product Backlog

Question 25

The Scrum Master notices that the Development Team is not following the Definition of Done consistently. What should the Scrum Master do?

Assign a team member to enforce compliance with the Definition of Done

Update the Definition of Done to match the current practices

Report the issue to the Product Owner

Correct answer

Coach the Development Team on the importance of the Definition of Done

Overall explanation

The Scrum Master should coach the Development Team on the importance of the Definition of Done, encourage self-accountability, and help them align their practices with the agreed-upon Definition of Done.

Domain

Scrum Master

Question 26

Scrum is founded on Systems Thinking and Lean Thinking.

Correct answer

FALSE

TRUE

Overall explanation

According to the Scrum guide: “Scrum is founded on empiricism and lean thinking. Empiricism asserts that knowledge comes from experience and making decisions based on what is observed. Lean thinking reduces waste and focuses on the essentials.”

Domain

Scrum

Question 27

What is the recommended maximum duration for a Sprint Retrospective for a two-weeks Sprint.

1 hour

2 hours

30 minutes

Correct answer

1 hour and 30 mins

Overall explanation

Sprint retrospectives are limited to a maximum of three hours. The general guidance is to allow 45 minutes for each week of sprint length. So a two-week sprint would cap the sprint retrospective at an hour and a half.

Domain

Sprint Retrospective

Question 28

Honesty is a Scrum Value

TRUE

Correct answer

FALSE

Overall explanation

This is not correct. The five Scrum Values are: Commitment, Courage, Focus, Openness, and Respect.

Domain

Scrum Values

Question 29

Which Scrum event is for gathering feedback from stakeholders to adapt the Product Backlog.

Release Planning

Sprint Retrospective

Demo

Correct answer

Sprint Review

Overall explanation

Only the Sprint Review event is an official Scrum to review the completed work and gather feedback from stakeholders to adapt the Product Backlog.

Domain

Sprint Review

Question 30

Who is responsible for managing the progress and completion of the work in the Sprint Backlog?

Correct answer

Development Team

Stakeholders

Scrum Master

Product Owner

Overall explanation

The Development Team is responsible for managing the progress and completion of the work in the Sprint Backlog during the Sprint.

Domain

Development Team

Question 31

Who is responsible for ensuring that the Development Team has a clear understanding of the items in the Product Backlog?

Stakeholders

Correct answer

Product Owner

Development Team

Scrum Master

Overall explanation

The Product Owner is responsible for ensuring that the Development Team has a clear understanding of the items in the Product Backlog.

Domain

Product Owner

Question 32

True or False: The Development Team can change the Sprint Goal during the Sprint.

Correct answer

FALSE

TRUE

Overall explanation

The Sprint Goal should remain unchanged once the Sprint has started to provide a clear focus for the Development Team.

Domain

Sprint Goal

Question 33

If multiple Scrum teams are working on a product, there would be multiple Product Backlogs.

TRUE

Correct answer

FALSE

Overall explanation

There would always be one Product Backlog and Product Owner for a product even when multiple teams are working on the Product.

Domain

Product Backlog

Question 34

True or False: The Development Team is responsible for estimating the effort required for Product Backlog items.

Correct answer

TRUE

FALSE

Overall explanation

The Development Team is responsible for estimating the effort required for Product Backlog items during Sprint Planning.

Domain

Development Team

Question 35

Who is responsible for ensuring that the Scrum artifacts are visible, transparent, and understood?

Stakeholders

Product Owner

Development Team

Correct answer

Scrum Master

Overall explanation

The Scrum Master is responsible for ensuring that the Scrum artifacts are visible, transparent, and understood by the Scrum Team and stakeholders.

Domain

Scrum Master

Question 36

Who is responsible for tracking the progress of the work towards the Sprint Goal in a non-software development company.

Product Owner

Stakeholders

Correct answer

Development Team

Scrum Master

Overall explanation

The Development Team is responsible for tracking the progress of the work towards the Sprint Goal and adapting as needed.

Domain

Development Team

Question 37

True or False: The Product Owner is responsible for enforcing the Scrum rules and practices.

TRUE

Correct answer

FALSE

Overall explanation

This is not correct. Only the Scrum Master is responsible for coaching and guiding the Scrum Team, not enforcing the rules and practices.

Domain

Scrum Master

Question 38

What is the recommended maximum duration for a Sprint Retrospective for a one month Sprint.

Correct answer

3 hours

1 hour

2 hours

30 minutes

Overall explanation

The Sprint Retrospective is a timebox of three hours or less for a one month sprint.

Domain

Sprint Retrospective

Question 39

During the Sprint Review, stakeholders provide feedback on the completed Increment. Some feedback requires major changes to the product. What should the Product Owner do?

Accept the feedback and immediately incorporate the changes

Disregard the feedback

Prioritize the feedback and plan for future iterations

Correct answer

Discuss the feedback with the stakeholders and determine the appropriate course of action

Overall explanation

The Product Owner should discuss the feedback with the stakeholders and determine the appropriate course of action, considering the impact on the product and its alignment with the overall product vision.

Domain

Sprint Review

Question 40

The Scrum Master notices that the Development Team is not conducting the Daily Scrum regularly. What action should the Scrum Master take?

Appoint a Project Manager

Cancel the Daily Scrum meetings

Assign a timekeeper role to monitor attendance and time

Correct answer

Facilitate and coach the team on the importance of the meeting

Overall explanation

The Scrum Master should facilitate the Development Team in conducting the Daily Scrum meetings, and put an emphasis on the importance of having them everyday during a Sprint.

Domain

Daily Scrum

Question 41

Daily Scrum is primarily a Status Update meeting.

TRUE

Correct answer

FALSE

Overall explanation

The primary purpose of the Daily Scrum is for Development Team members to sync, identify and bottlenecks and plan their work for the day.

Domain

Daily Scrum

Question 42

True or False: The Product Owner is responsible for creating the Sprint Backlog.

Correct answer

FALSE

TRUE

Overall explanation

The Development Team is responsible for creating the Sprint Backlog during Sprint Planning based on the Product Backlog items selected for the Sprint.

Domain

Development Team

Question 43

Who is responsible for updating the progress of the work on the Scrum board during the Daily Scrum?

Scrum Master

Correct answer

Development Team

Stakeholders

Product Owner

Overall explanation

The Development Team is responsible for updating the progress of the work on the Scrum board during the Daily Scrum.

Domain

Development Team

Question 44

What is the recommended timebox for the Daily Scrum?

45 minutes

1 hour

30 minutes

Correct answer

15 minutes

Overall explanation

The recommended timebox for the Daily Scrum is 15 minutes to keep the meeting focused and efficient.

Domain

Daily Scrum

Question 45

True or False: The organization human resources is responsible for coaching the Scrum rules and practices.

Correct answer

FALSE

TRUE

Overall explanation

It is not the Human Resources but the Scrum Master who is responsible for coaching and facilitating the Scrum Team.

Domain

Scrum Master

Question 46

Who is responsible for managing the progress and completion of the work in the Sprint Backlog?

Correct answer

Development Team

Product Owner

Stakeholders

Scrum Master

Overall explanation

The Development Team is responsible for managing the progress and completion of the work in the Sprint Backlog during the Sprint.

Domain

Development Team

Question 47

True or False: The Product Owner is responsible for estimating the effort required for Product Backlog items.

FALSE

Correct answer

TRUE

Overall explanation

The Development Team is responsible for estimating the effort required for Product Backlog items during Sprint Planning.

Domain

Development Team

Question 48

What is the recommended maximum duration for a Sprint Retrospective?

Correct answer

3 hours

1 hour

30 minutes

2 hours

Overall explanation

The recommended maximum duration for a Sprint Retrospective is 3 hours for a one-month Sprint, allowing sufficient time for meaningful discussions and improvement planning.

Domain

Sprint Retrospective

Question 49

The Scrum Master observes that the Development Team is not adhering to the Scrum framework and its principles. What should the Scrum Master do?

Enforce strict compliance with the Scrum framework

Report the issue to the Product Owner

Correct answer

Coach and guide the Development Team on Scrum principles

Assign tasks to the Development Team to ensure adherence

Overall explanation

The Scrum Master should coach and guide the Development Team on Scrum principles, promoting self-organization and understanding of the framework’s benefits.

Domain

Scrum Master

Question 50

What is the primary purpose of the Daily Scrum?

To review the completed work

Correct answer

Sync with development team and discuss any issues

To discuss the work for the next the days

To assign tasks to the team

Overall explanation

The primary purpose of the Daily Scrum is to provide a status update and synchronize the Development Team’s work.

Domain

Daily Scrum

Question 51

Commitment is a Scrum Value

FALSE

Correct answer

TRUE

Overall explanation

This is correct. The five Scrum Values are: Commitment, Courage, Focus, Openness, and Respect.

Domain

Scrum Values

Question 52

The Scrum Team realizes that one of the selected Sprint Backlog items is too complex to complete within the Sprint. What should they do?

Extend the Sprint to accommodate the complex item

Remove the item from the Sprint Backlog

Correct answer

Break down the item into smaller, manageable parts

Seek approval from the Product Owner to add more resources

Overall explanation

The Scrum Team should collaborate to break down the complex item into smaller, manageable parts that can be completed within the Sprint timebox, maintaining the integrity of the Sprint Backlog.

Domain

Sprint Planning

Question 53

Who is responsible for ordering the items in the Product Backlog?

Scrum Master

Stakeholders

Correct answer

Product Owner

Development Team

Overall explanation

The Product Owner is responsible for ordering the items in the Product Backlog based on their value and priorities.

Domain

Product Owner

Question 54

What is the recommended timebox for the Sprint Planning event for a Sprint of one week.

Correct answer

2 hours

8 hours

4 hours

1 hour

Overall explanation

The recommended timebox for the Sprint Planning event is 2 hours for a one-week Sprint, allowing sufficient time for collaborative planning and goal setting.

Domain

Sprint Planning

Question 55

Definition of Ready is mandatory in Scrum.

Correct answer

FALSE

TRUE

Overall explanation

There is no official concept for Definition of Ready in Scrum.

Domain

Definition of Done

Question 56

True or False: The Scrum Master is responsible for managing the Product Backlog.

FALSE

Correct answer

TRUE

Overall explanation

The Product Owner is responsible for managing the Product Backlog, including prioritizing and refining the items.

Domain

Scrum Master

Question 57

True or False: The Development Team is responsible for managing the Product Backlog.

Correct answer

FALSE

TRUE

Overall explanation

The Product Owner is responsible for managing the Product Backlog, including prioritization and refinement.

Domain

Product Owner

Question 58

What is the primary purpose of the Sprint Planning?

To review the completed work

Correct answer

To create a plan for the Sprint

To assign tasks to the team

To inspect and adapt the process

Overall explanation

The primary purpose of the Sprint Planning is to create a plan for the upcoming Sprint, including the Sprint Goal and selected Product Backlog

Domain

Sprint Planning

Question 59

Courage is a pillar of Scrum

Correct answer

FALSE

TRUE

Overall explanation

Courage is a Scrum Value and not a Scrum Pillar.

Domain

Scrum Values

Question 60

Who is responsible for tracking the progress of the work towards the Sprint Goal?

Stakeholders

Correct answer

Development Team

Scrum Master

Product Owner

Overall explanation

The Development Team is responsible for tracking the progress of the work towards the Sprint Goal and adapting as needed.

Domain

Development Team

Question 61

Who is responsible for updating the progress of the work in the Sprint Backlog when the Development Team is working remotely.

Correct answer

Development Team

Product Owner

Stakeholders

Scrum Master

Overall explanation

The Development Team is responsible for updating the progress of the work in the Sprint Backlog during the Sprint.

Domain

Development Team

Question 62

The Product Owner identifies new features that would enhance the product. What should the Product Owner do?

Add new resources to the team to start work immediately

Immediately interrupt the Sprint to add it to the ongoing work

Correct answer

Break it down into smaller items and add it to the Product Backlog for future prioritization

Inform the Development Team during the Daily Scrum

Overall explanation

The Product Owner should break it down into smaller items and add it to the Product Backlog for future prioritization.

Domain

Product Backlog

Question 63

Definition of Done is not mandatory in Scrum.

TRUE

Correct answer

FALSE

Overall explanation

The Definition of Done is required in Scrum.

Domain

Definition of Done

Question 64

Who is responsible for updating the progress of the work in the Sprint Backlog?

Stakeholders

Product Owner

Correct answer

Development Team

Scrum Master

Overall explanation

The Development Team is responsible for updating the progress of the work in the Sprint Backlog during the Sprint.

Domain

Development Team

Question 65

Who is responsible for ensuring that the Development Team understands and works towards the Sprint Goal?

Product Owner

Correct answer

Development Team

Stakeholders

Scrum Master

Overall explanation

The Development Team is responsible for understanding and working towards the Sprint Goal as a collective effort.

Domain

Development Team

Question 66

Who is responsible for tracking and making the progress of the work visible during the Sprint?

Scrum Master

Product Owner

Correct answer

Development Team

Stakeholders

Overall explanation

The Development Team is responsible for tracking and making the progress of the work visible during the Sprint.

Domain

Development Team

Question 67

Who is responsible for ensuring that the Scrum Team understands and adheres to the Scrum framework?

Development Team

Stakeholders

Correct answer

Scrum Master

Product Owner

Overall explanation

The Scrum Master is responsible for ensuring that the Scrum Team understands and adheres to the Scrum framework.

Domain

Scrum Master

Question 68

The Scrum Master notices that the Development Team is not following the Definition of Done consistently. What should the Scrum Master do?

Correct answer

Coach the Development Team on the importance of the Definition of Done

Update the Definition of Done to match the current practices

Assign a team member to enforce compliance with the Definition of Done

Report the issue to the Product Owner

Overall explanation

The Scrum Master should coach the Development Team on the importance of the Definition of Done, encourage self-accountability, and help them align their practices with the agreed-upon Definition of Done.

Domain

Scrum Master

Question 69

Select the correct Scrum Values.

Transparency

Dedication

Inspection

Correct selection

Focus

Correct selection

Respect

Overall explanation

The five Scrum Values are: Commitment, Courage, Focus, Openness, and Respect.

Domain

Scrum Values

Question 70

Scrum requires the entire Development Team to attend the Release Planning event.

TRUE

Correct answer

FALSE

Overall explanation

This is not correct as Release Planning is not a Scrum event.

Domain

Scrum Events

Question 71

The Sprint Retrospective has concluded, and the Development Team has identified several process improvements. How should they proceed?

Correct answer

Prioritize the improvements and create action items

Ignore the improvements and continue with the current process

Share the improvements with stakeholders

Implement the improvements in the next Sprint

Overall explanation

The Development Team should prioritize the identified improvements, create action items, and implement them in the next Sprint to foster continuous improvement.

Domain

Sprint Retrospective

Question 72

True or False: The Scrum Master is responsible for enforcing the Scrum rules and practices.

TRUE

Correct answer

FALSE

Overall explanation

The Scrum Master is responsible for coaching and facilitating the Scrum Team, not enforcing the rules and practices.

Domain

Scrum Master

Question 73

During Sprint Planning, the Development Team realizes that they have more work than they can complete within the Sprint timebox. What should they do?

Reduce the scope of the Sprint

Correct answer

All of the above

Extend the Sprint duration

Collaborate with the Product Owner to reprioritize the backlog

Overall explanation

The Development Team should collaborate with the Product Owner to reprioritize the backlog, considering the work that can be completed within the Sprint timebox.

Domain

Sprint Planning

Question 74

True or False: The Sprint Review is an opportunity to inspect the Increment and adapt the Product Backlog.

Correct answer

TRUE

FALSE

Overall explanation

The Sprint Review provides an opportunity to inspect the Increment and adapt the Product Backlog based on stakeholder feedback.

Domain

Sprint Review

Question 75

Product Owner attendance is mandatory in the Daily Scrum?

Correct answer

FALSE

TRUE

Overall explanation

This is not correct. The Daily Scrum is meant for the Development Team and not the Product Owner.

Domain

Daily Scrum

Question 76

What is the primary purpose of the Sprint Retrospective?

To review the completed work

To plan the next Sprint

To showcase the Increment

Correct answer

To inspect and adapt the process

Overall explanation

The primary purpose of the Sprint Retrospective is to inspect and adapt the process, identifying improvements for the next Sprint.

Domain

Sprint Retrospective

Question 77

True or False: The Scrum Master is responsible for prioritizing the Product Backlog.

Correct answer

TRUE

FALSE

Overall explanation

The Product Owner is responsible for prioritizing the Product Backlog based on value and stakeholder needs.

Domain

Product Owner

Question 78

The Scrum Master notices that the Daily Scrum meetings are exceeding the timebox consistently. What action should the Scrum Master take?

Correct answer

Facilitate the team in keeping the meetings within the timebox

Cancel the Daily Scrum meetings to save time

Assign a timekeeper role to manage the time

Extend the timebox for the Daily Scrum meetings

Overall explanation

The Scrum Master should facilitate the Development Team in keeping the Daily Scrum meetings within the timebox, ensuring that discussions are focused and time is managed effectively.

Domain

Daily Scrum

Question 79

What is the purpose of the Sprint Review event?

To review the completed work

Correct answer

To gather feedback from stakeholders

To inspect and adapt the process

To create a detailed project plan

Overall explanation

The purpose of the Sprint Review event is to review the completed work, gather feedback from stakeholders, and inspect and adapt the Product Backlog.

Domain

Sprint Review

Question 80

In Scrum, what is the primary responsibility of the Product Owner?

To define the product features

Correct answer

To prioritize the Product Backlog

To deliver a potentially releasable Increment

To manage the Development Team

Overall explanation

The primary responsibility of the Product Owner is to prioritize the Product Backlog based on value and ensure the Development Team understands the requirements.

Domain

Product Owner