PSM-I.001.075
Question 75
The Scrum Master observes that the Development Team is not adhering to the agreed-upon Scrum events and time-boxes. What should the Scrum Master do to address this issue?
Facilitate a discussion with the Development Team to understand the reasons behind the non-adherence and address any concerns.
Collaborate with the Product Owner to review and adjust the Scrum events and timeboxes.
Reinforce the importance of Scrum events and time-boxes, highlighting the benefits they provide.
Enforce strict rules and penalties for nonadherence to Scrum events and timeboxes.
Overall explanation
In this scenario, the Scrum Master should facilitate a discussion with the Development Team to understand the reasons behind the non-adherence and address any concerns. They should also reinforce the importance of Scrum events and time-boxes, highlighting the benefits they provide.
Domain
Scrum