PSM-I.001.034
January 12, 2025
Question 34
True or False: The Sprint Backlog is a forecast of work to be done and may be adjusted throughout the Sprint as more information becomes available.
FALSE
TRUE
Overall explanation
The Sprint Backlog is a forecast of work to be done during the Sprint. As the Development Team learns more, new information emerges, or priorities change, they can collaborate with the Product Owner to add, remove, or reorder the items in the Sprint Backlog. Adjustments are expected and can be made to reflect the current understanding and needs.
Domain
Artifacts