PSM-I.001.014 The Product Owner wants to include a large new feature in the current Sprint
Question 14
The Product Owner wants to include a large new feature in the current Sprint. The Development Team determines that it cannot be completed within the Sprint time frame. What should they do?
Discuss the feature’s complexity and feasibility with the Product Owner and stakeholders.
Reject the feature request and proceed with the originally planned Sprint Backlog.
Collaborate with the Product Owner to break down the feature into smaller, deliverable increments.
Add the feature to the Product Backlog and address it in future Sprints.
Overall explanation
In this scenario, the Development Team should collaborate with the Product Owner to break down the large feature into smaller, deliverable increments. They should also discuss the feature’s complexity and feasibility with the Product Owner and stakeholders to find a suitable solution.
Domain
Scrum