PSM-I.001.080

Question 80

The Development Team realizes that the Sprint Goal is no longer achievable due to unforeseen technical complexities. What should they do?

Continue with the original Sprint Goal and accept the potential risk of not meeting it.

Cancel the current Sprint and start a new one with a revised goal.

Collaborate with the Product Owner to redefine the Sprint Goal and adjust the Sprint Backlog accordingly.

Seek assistance from the Scrum Master to address the technical complexities.

Overall explanation

In this scenario, the Development Team should seek Scrum Master help in addressing of technical complexities. They should still aim for moving towards the Sprint Goal until the end of the Sprint.

Domain

Scrum