PSM-I.001.007 During the Sprint, a critical dependency is identified that could impact the completion of a Product Backlog item

Question 7

During the Sprint, a critical dependency is identified that could impact the completion of a Product Backlog item. What should the Development Team do now in this situation?

  • Adjust the Sprint Goal to accommodate the dependency and update the Sprint Backlog.

  • Communicate the issue to the Scrum Master and seek assistance in resolving the dependency.

  • Engage with external teams or resources to resolve the dependency.

  • Collaborate with the Product Owner and stakeholders to reassess the priority and explore alternative options.

Overall explanation

In this scenario, the Development Team should collaborate with the Product Owner and stakeholders to reassess the priority of the affected item and explore alternative options. They should also communicate the issue to the Scrum Master, who can assist in resolving the dependency or provide guidance on how to address it effectively.

Domain

Scrum