PSM-I.004 Scrum Master Mock Exam Simulator 4

Scrum Master Mock Exam Simulator 4 – Results

Back to result overview

AttemptĀ 1

All domains

  • 80 all
  • 0 correct
  • 0 incorrect
  • 80
  • 0 marked

Collapse all questions

Question 1

In Scrum, who is responsible for ensuring that the selected Product Backlog items meet the Definition of Ready?

Correct answer

Development Team

Product Owner

Scrum Master

Stakeholders

Overall explanation

The Development Team is responsible for ensuring that the selected Product Backlog items meet the Definition of Ready by collaborating with the Product Owner and clarifying any ambiguities.

Domain

Product Backlog

Question 2

True or False: The Scrum framework prescribes specific documentation requirements.

TRUE

Correct answer

FALSE

Overall explanation

The Scrum framework does not prescribe specific documentation requirements. It encourages capturing essential information while allowing flexibility based on the needs of the project.

Domain

Scrum Framework

Question 3

True or False: The Scrum framework prescribes specific tools or technologies to be used.

TRUE

Correct answer

FALSE

Overall explanation

The Scrum framework does not prescribe specific tools or technologies. It emphasizes the importance of individuals and interactions over tools and promotes adaptable approaches.

Domain

Scrum Framework

Question 4

In Scrum, who is responsible for ensuring that the selected Product Backlog items meet the Definition of Ready?

Correct answer

Development Team

Stakeholders

Scrum Master

Product Owner

Overall explanation

The Development Team is responsible for ensuring that the selected Product Backlog items meet the Definition of Ready by collaborating with the Product Owner and clarifying any ambiguities.

Domain

Product Backlog

Question 5

What is the maximum duration for a Sprint in Scrum when the team size is small.

It can vary depending on the nature of the project

Two weeks

One week

Correct answer

One month

Overall explanation

The maximum duration for a Sprint in Scrum is four weeks.

Domain

Sprint Duration

Question 6

True or False: The Product Owner is solely responsible for estimating the effort required to complete the Product Backlog items.

Correct answer

FALSE

TRUE

Overall explanation

Estimating the effort required to complete the Product Backlog items is a collaborative effort involving the Development Team and other stakeholders, not solely the Product Owner.

Domain

Product Owner

Question 7

What is the recommended frequency for holding the Sprint Retrospective event in Scrum when the same team is working together for more than 10 Sprints?

Every month

Every other Sprint

Every quarter

Correct answer

Every Sprint

Overall explanation

The Sprint Retrospective event should be held at the end of every Sprint to reflect on the previous Sprint and identify areas for improvement in the next Sprint.

Domain

Sprint Retrospective

Question 8

True or False: The Product Owner is responsible for assigning tasks to individual Development Team members when he/she feels work is not progressing well.

TRUE

Correct answer

FALSE

Overall explanation

The Product Owner does not assign tasks to individual Development Team members. The Development Team self-organizes and determines how to accomplish the work.

Domain

Scrum Master Role

Question 9

For big products, there can be two Product Owners within the same Scrum Team?

TRUE

Correct answer

FALSE

Overall explanation

There can only be one Product Owner within a Scrum Team.

Domain

Product Owner

Question 10

What is the purpose of the Sprint Retrospective event in Scrum?

To review and adjust the Product Backlog

Correct answer

To inspect and adapt the Scrum Team’s processes

To demonstrate the Increment to stakeholders

To plan the work for the next Sprint

Overall explanation

The purpose of the Sprint Retrospective is to inspect and adapt the Scrum Team’s processes, identify improvements, and plan adjustments for the next Sprint.

Domain

Sprint Retrospective

Question 11

Who is responsible for defining the Sprint Goal?

Development Team

Scrum Master

Product Owner

Correct answer

Scrum Team

Overall explanation

The entire Scrum Team, including the Product Owner, Development Team, and Scrum Master, collaboratively defines the Sprint Goal during the Sprint Planning event.

Domain

Sprint Goal

Question 12

True or False: The Scrum framework prescribes best practices, coding guidelines and leading industry standards that the Development Team must follow.

Correct answer

FALSE

TRUE

Overall explanation

The statement is false. The Scrum framework does not prescribe such things.

Domain

Scrum Framework

Question 13

Which statement best describes the concept of "Sprint Goal" in Scrum?

It is a target velocity to achieve by the end of the Sprint

Correct answer

It is a high-level objective or outcome for the Sprint

It is a detailed list of tasks for the Development Team to complete

It is the estimated amount of work that can be completed in the Sprint

Overall explanation

The Sprint Goal is a high-level objective or outcome that provides focus and coherence to the work undertaken in the Sprint.

Domain

Sprint Goal

Question 14

What is the purpose of the Sprint Planning event in Scrum?

To estimate the work required for the selected Product Backlog items

To create a detailed schedule for the Sprint

To update the Product Backlog with new items

Correct answer

To define the Sprint Goal and plan the work for the Sprint

Overall explanation

The purpose of the Sprint Planning event is to define the Sprint Goal, select the Product Backlog items for the Sprint, and create a plan for achieving the Sprint Goal.

Domain

Sprint Planning

Question 15

True or False: The Scrum framework prescribes specific software development practices.

TRUE

Correct answer

FALSE

Overall explanation

The Scrum framework does not prescribe specific software development practices. It is a framework that can be used with different software development approaches.

Domain

Scrum Framework

Question 16

True or False: The Scrum Master is a management position with authority over the Development Team.

Correct answer

FALSE

TRUE

Overall explanation

The statement is false. The Scrum Master is not a management position with authority over the Development Team. The Scrum Master serves as a servant-leader and facilitator for the Scrum Team.

Domain

Scrum Master Role

Question 17

True or False: The Development Team is responsible for coordinating with stakeholders and managing their expectations.

TRUE

Correct answer

FALSE

Overall explanation

The Development Team collaborates with stakeholders but is not responsible for coordinating with them or managing their expectations. This is primarily the role of the Product Owner.

Domain

Development Team

Question 18

In Scrum, who is responsible for prioritizing the Product Backlog?

Stakeholders

Correct answer

Product Owner

Scrum Master

Development Team

Overall explanation

The Product Owner is responsible for prioritizing the Product Backlog based on the value and insights from stakeholders and the Development Team.

Domain

Product Backlog

Question 19

True or False: The Development Team is responsible for selecting the items from the Product Backlog for the Sprint.

FALSE

Correct answer

TRUE

Overall explanation

The Development Team, in collaboration with the Product Owner, is responsible for selecting the items from the Product Backlog for the Sprint during the Sprint Planning event.

Domain

Development Team

Question 20

What is the purpose of the Sprint Review in Scrum?

To evaluate the performance of individual team members

To inspect the Increment and adapt the Product Backlog

To review and approve changes to the Product Backlog

Correct answer

To showcase the completed Increment to stakeholders

Overall explanation

The purpose of the Sprint Review is to showcase the completed Increment to stakeholders and gather feedback to adapt the Product Backlog.

Domain

Sprint Review

Question 21

True or False: The Scrum framework is suitable only for software development projects.

Correct answer

FALSE

TRUE

Overall explanation

Scrum can be applied to various types of projects beyond software development, including product development and other complex projects.

Domain

Scrum Framework

Question 22

What is the primary purpose of the Sprint Review in Scrum?

Correct answer

To showcase the completed Increment to stakeholders

To inspect the Increment and adapt the Product Backlog

To review and approve changes to the Product Backlog

To evaluate the performance of individual team members

Overall explanation

The primary purpose of the Sprint Review is to showcase the completed Increment to stakeholders and gather feedback to adapt the Product Backlog.

Domain

Sprint Review

Question 23

In Scrum, who is responsible for managing the progress of the work during a Sprint when it is the first Sprint for a new product?

Product Owner

Stakeholders

Correct answer

Development Team

Scrum Master

Overall explanation

The Development Team is responsible for managing the progress of the work during a Sprint and ensuring transparency of their progress to the stakeholders.

Domain

Development Team

Question 24

What is the recommended maximum duration for a Sprint Review for a Scrum Team having less than 9 developers.

Correct answer

1 hour

3 hours

2 hours

4 hours

Overall explanation

The recommended maximum duration for a Sprint Review is 1 hour. It allows for effective inspection and adaptation while ensuring the event does not become overly time-consuming.

Domain

Sprint Review

Question 25

Who is responsible for creating and maintaining the Sprint Backlog when the Development Team is less experienced?

Scrum Master

Correct answer

Development Team

Stakeholders

Product Owner

Overall explanation

The Development Team is responsible for creating and maintaining the Sprint Backlog, based on the selected Product Backlog items and their commitment to the Sprint Goal.

Domain

Sprint Backlog

Question 26

True or False: The Product Owner is solely responsible for maintaining and updating the Product Backlog and any collaboration is prohibited.

TRUE

Correct answer

FALSE

Overall explanation

The statement is false. While the Product Owner is primarily responsible for maintaining and updating the Product Backlog, it is a collaborative effort involving input from the Development Team and stakeholders.

Domain

Product Backlog

Question 27

True or False: The Scrum Master is responsible for assigning tasks to the Development Team members.

TRUE

Correct answer

FALSE

Overall explanation

The Scrum Master is not responsible for assigning tasks to the Development Team members. The team self-organizes and collaboratively determines how to accomplish the Sprint Backlog items.

Domain

Scrum Master Role

Question 28

True or False: The Scrum framework prescribes specific project management methodologies.

Correct answer

FALSE

TRUE

Overall explanation

The Scrum framework does not prescribe specific project management methodologies. It is a lightweight framework for agile product development.

Domain

Scrum Framework

Question 29

Who is responsible for making sure the Development Team understands the Product Goal and the Sprint Goal?

Stakeholders

Development Team

Scrum Master

Correct answer

Product Owner

Overall explanation

The Product Owner is responsible for making sure the Development Team understands the Product Goal and the Sprint Goal, ensuring alignment and clarity on the desired outcomes.

Domain

Product Owner

Question 30

True or False: The Sprint Backlog is a dynamic document that is updated throughout the Sprint as new information emerges.

Correct answer

TRUE

FALSE

Overall explanation

The statement is true. The Sprint Backlog is a dynamic document that is updated throughout the Sprint as new information emerges and the Development Team learns more.

Domain

Sprint Backlog

Question 31

In Scrum, who is responsible for managing the progress of the work during a Sprint when the organization has a dedicated Compliance Team?

Scrum Master

Correct answer

Development Team

Product Owner

Stakeholders

Overall explanation

The Development Team is responsible for managing the progress of the work during a Sprint and ensuring transparency of their progress to the stakeholders.

Domain

Development Team

Question 32

Who is responsible for managing the progress of the work during a Sprint?

Stakeholders

Product Owner

Correct answer

Development Team

Scrum Master

Overall explanation

The Development Team is responsible for managing the progress of the work during a Sprint and ensuring transparency of their progress to the stakeholders.

Domain

Development Team

Question 33

What is the primary purpose of the Daily Scrum in non-software development Scrum Teams.

To plan the work for the day

To evaluate the performance of individual team members

To provide a status update to the Product Owner

Correct answer

To identify any obstacles or impediments

Overall explanation

The primary purpose of the Daily Scrum is to identify any obstacles or impediments that may affect the Development Team’s progress and collaborate on finding solutions.

Domain

Daily Scrum

Question 34

True or False: The Scrum Master is responsible for ensuring that the Scrum Team has a clear understanding of the work to be done.

Correct answer

TRUE

FALSE

Overall explanation

The Scrum Master is responsible for ensuring that the Scrum Team has a clear understanding of the work to be done, facilitating effective communication and collaboration.

Domain

Scrum Master Role

Question 35

Who is responsible for removing any obstacles that hinder the progress of the Development Team?

Product Owner

Development Team

Stakeholders

Correct answer

Scrum Master

Overall explanation

The Scrum Master is responsible for removing obstacles that hinder the progress of the Development Team, facilitating their work and ensuring a productive and uninterrupted workflow.

Domain

Scrum Master Role

Question 36

Who is responsible for ensuring that the Development Team understands the purpose and value of the work they undertake in a Sprint?

Scrum Master

Correct answer

Development Team

Stakeholders

Product Owner

Overall explanation

The Development Team is responsible for understanding the purpose and value of the work they undertake in a Sprint, ensuring their commitment and alignment with the Sprint Goal.

Domain

Development Team

Question 37

The Development Team cant start work until the entire Product Backlog is complete.

Correct answer

FALSE

TRUE

Overall explanation

This is not correct. The Product Backlog is an emergent, ordered list of what is needed to improve the product. It is a live document that will always keep on changing.

Domain

Product Backlog

Question 38

What is the purpose of the Sprint Retrospective in Scrum?

To review and adapt the Sprint Backlog

Correct answer

To reflect on the team’s performance and identify improvements

To evaluate the performance of individual team members

To showcase the completed Increment to stakeholders

Overall explanation

The purpose of the Sprint Retrospective is to reflect on the team’s performance, identify areas of improvement, and create a plan for implementing changes in the next Sprint.

Domain

Sprint Retrospective

Question 39

Who is responsible for managing the Product Backlog during a Sprint?

Correct answer

Product Owner

Stakeholders

Scrum Master

Development Team

Overall explanation

The Product Owner is responsible for managing the Product Backlog during a Sprint, ensuring it is refined, reprioritized, and aligned with the Sprint Goal.

Domain

Product Backlog

Question 40

In Scrum, who is responsible for resolving conflicts and removing any impediments that hinder the Development Team’s progress?

Correct answer

Scrum Master

Product Owner

Stakeholders

Development Team

Overall explanation

The Scrum Master is responsible for resolving conflicts and removing any impediments that hinder the Development Team’s progress, enabling them to focus on delivering the Sprint Goal.

Domain

Scrum Master Role

Question 41

What is the recommended maximum duration for a Daily Scrum when held at the beginning of a working week.

45 minutes

30 minutes

Correct answer

15 minutes

1 hour

Overall explanation

The recommended maximum duration for a Daily Scrum is 15 minutes. It promotes focus, quick updates, and efficient coordination without consuming excessive time.

Domain

Daily Scrum

Question 42

Product Owner is supposed to be present for the Sprint Retrospective event.

TRUE

Correct answer

FALSE

Overall explanation

Product Owner participation is required for the Sprint Retrospective.

Domain

Sprint Retrospective

Question 43

Who is responsible for ensuring that the Development Team has the necessary skills and resources to achieve the Sprint Goal?

Stakeholders

Correct answer

Development Team

Scrum Master

Product Owner

Overall explanation

The Development Team is responsible for ensuring that they have the necessary skills and resources to achieve the Sprint Goal, fostering self-organization and continuous improvement.

Domain

Development Team

Question 44

True or False: The Scrum Master is a management position with authority over the Development Team.

TRUE

Correct answer

FALSE

Overall explanation

The Scrum Master is not a management position with authority over the Development Team. The Scrum Master serves as a servant-leader and facilitator for the Scrum Team.

Domain

Scrum Master Role

Question 45

Who is responsible for ensuring that the Scrum events are timeboxed and effectively conducted?

Development Team

Product Owner

Correct answer

Scrum Master

Stakeholders

Overall explanation

The Scrum Master is responsible for ensuring that the Scrum events are timeboxed and effectively conducted, enabling valuable collaboration and maximizing their purpose.

Domain

Scrum Master Role

Question 46

True or False: The Scrum framework prescribes specific engineering practices and techniques.

TRUE

Correct answer

FALSE

Overall explanation

The Scrum framework does not prescribe specific engineering practices and techniques. It focuses on the roles, events, artifacts, and values of Scrum.

Domain

Scrum Framework

Question 47

What is the recommended duration for a Sprint in Scrum involving a product to be launched in more than a year.

3 weeks

1 month

2 weeks

Correct answer

4 weeks

Overall explanation

The recommended duration for a Sprint in Scrum is 2 weeks. It allows for frequent inspection and adaptation while providing a reasonable timeframe for delivering valuable increments.

Domain

Sprint Duration

Question 48

When the Development Team has more developers, the daily Scrum Team duration would get changed?

Correct answer

FALSE

TRUE

Overall explanation

The number of Developers has no impact on the maximum duration (15 minutes) for the Daily Scrum.

Domain

Daily Scrum

Question 49

What is the purpose of the Sprint Review event in Scrum?

To inspect and adapt the progress towards the Sprint Goal

To review and adjust the Product Backlog

Correct answer

To demonstrate the Increment to stakeholders

To plan the work for the next Sprint

Overall explanation

The purpose of the Sprint Review is to demonstrate the Increment to stakeholders, gather feedback, and inspect and adapt the progress towards the Sprint Goal.

Domain

Sprint Review

Question 50

Who is responsible for ensuring that the Sprint Backlog is visible and up-to-date?

Product Owner

Scrum Master

Stakeholders

Correct answer

Development Team

Overall explanation

The Development Team is responsible for ensuring that the Sprint Backlog is visible and up-to-date, providing transparency on the progress and work remaining in the Sprint.

Domain

Sprint Backlog

Question 51

What is the purpose of the Sprint Retrospective in Scrum?

To review and adapt the Sprint Backlog

Correct answer

To reflect on the team’s performance and identify improvements

To evaluate the performance of individual team members

To showcase the completed Increment to stakeholders

Overall explanation

The purpose of the Sprint Retrospective is to reflect on the team’s performance, identify areas of improvement, and create a plan for implementing changes in the next Sprint.

Domain

Sprint Retrospective

Question 52

True or False: The Development Team can make changes to the selected Product Backlog items during a Sprint.

FALSE

Correct answer

TRUE

Overall explanation

The statement is true. The Development Team can make changes to the selected Product Backlog items during a Sprint if it helps to achieve the Sprint Goal and meets the Definition of Done.

Domain

Development Team

Question 53

Who is responsible for prioritizing the Product Backlog items?

Stakeholders

Scrum Master

Correct answer

Product Owner

Development Team

Overall explanation

The Product Owner is responsible for prioritizing the Product Backlog items, considering the needs of the stakeholders and maximizing the value delivered by the Scrum Team.

Domain

Product Backlog

Question 54

In Scrum, who is responsible for prioritizing the Product Backlog?

Development Team

Scrum Master

Correct answer

Product Owner

Stakeholders

Overall explanation

The Product Owner is responsible for prioritizing the Product Backlog based on the value and insights from stakeholders and the Development Team.

Domain

Product Backlog

Question 55

Who is responsible for conducting the Sprint Review event?

Scrum Master

Correct answer

Product Owner

Stakeholders

Development Team

Overall explanation

The Product Owner is responsible for conducting the Sprint Review event, facilitating the demonstration of the Increment to stakeholders and gathering their valuable feedback.

Domain

Sprint Review

Question 56

True or False: The Scrum framework prescribes specific engineering practices and technical practices that the Development Team must follow.

Correct answer

FALSE

TRUE

Overall explanation

The statement is false. The Scrum framework does not prescribe specific engineering or technical practices. The Development Team is responsible for selecting and implementing appropriate practices.

Domain

Scrum Framework

Question 57

Who is responsible for managing the Product Backlog and ensuring that it is transparent, ordered, and properly refined?

Scrum Master

Stakeholders

Development Team

Correct answer

Product Owner

Overall explanation

The Product Owner is responsible for managing the Product Backlog and ensuring its transparency, order, and refinement to maximize value delivery.

Domain

Product Backlog

Question 58

Who is responsible for ensuring that the Sprint Backlog is visible and up-to-date?

Scrum Master

Stakeholders

Product Owner

Correct answer

Development Team

Overall explanation

The Development Team is responsible for ensuring that the Sprint Backlog is visible and up-to-date, providing transparency on the progress and work remaining in the Sprint.

Domain

Sprint Backlog

Question 59

Who has the authority to cancel a Sprint when the Sprint Goal becomes obsolete.

Scrum Master

Correct answer

Product Owner

Development Team

Stakeholders

Overall explanation

A Sprint could be cancelled if the Sprint Goal becomes obsolete. Only the Product Owner has the authority to cancel the Sprint.

Domain

Sprint

Question 60

Who is responsible for ensuring that the Scrum Team understands and adheres to the Scrum framework?

Scrum Master and Project Management Office

Scrum Master and Human Resources Department

Correct answer

Scrum Master

Scrum Master and Product Owner

Overall explanation

The Scrum Master is responsible for ensuring that the Scrum Team understands and adheres to the Scrum framework, facilitating its implementation and guiding the team’s adoption.

Domain

Scrum Master Role

Question 61

Who is responsible for managing the Product Backlog in Scrum?

Stakeholders

Correct answer

Product Owner

Scrum Master

Development Team

Overall explanation

The Product Owner is responsible for managing the Product Backlog, including its content, ordering, and ensuring its transparency to stakeholders.

Domain

Product Backlog

Question 62

When should the increment be released.

At the conclusion of a Sprint

When increment is ready

Correct answer

When the Scrum Teams decides to release

When market conditions are good

Overall explanation

When the Scrum Team decides, the increment can be released.

Domain

Development Team

Question 63

Which statement best describes the concept of "Sprint Goal" in Scrum?

It is a measure of success of how the organization is progressing.

Correct answer

It communicates why the Sprint is of value to its customers and/or users.

It is the estimated amount of work that can be completed in the Sprint

It is a detailed list of tasks for the Development Team to complete

Overall explanation

The Sprint Goal is a high-level objective or outcome that provides focus and coherence to the work undertaken in the Sprint.

Domain

Sprint Goal

Question 64

Who is responsible for ensuring that the Sprint Retrospective is conducted and its outcomes are acted upon?

Development Team

Product Owner

Correct answer

Scrum Master

Stakeholders

Overall explanation

The Scrum Master is responsible for ensuring that the Sprint Retrospective is conducted and its outcomes are acted upon, promoting continuous improvement and adaptation.

Domain

Scrum Master Role

Question 65

During a Sprint, the Development Team determines that it won’t be able to complete all the selected Product Backlog items. What should the Development Team do?

Correct answer

Inform the Product Owner and negotiate new commitments

Extend the Sprint duration to accommodate the remaining work

Skip those items and continue with the Sprint

Add the unfinished items to the next Sprint

Overall explanation

The Development Team should inform the Product Owner and negotiate new commitments based on the capacity and available time in the Sprint.

Domain

Sprint Planning

Question 66

True or False: The Scrum framework can be applied to any project or product development effort.

FALSE

Correct answer

TRUE

Overall explanation

The Scrum framework is flexible and can be applied to various project or product development efforts, enabling iterative and incremental delivery.

Domain

Scrum Framework

Question 67

True or False: The Sprint Review is an opportunity for the Development Team to inspect and adapt their working methods.

TRUE

Correct answer

FALSE

Overall explanation

The statement is false. The Sprint Retrospective provides an opportunity for the Scrum Team to inspect their working methods, gather feedback, and identify areas for improvement in the next Sprint.

Domain

Sprint Review

Question 68

Sprint Planning event in Scrum is an opportunity to find ways how can previous discontinued work be continued in the current Sprint.

TRUE

Correct answer

FASLE

Overall explanation

The purpose of the Sprint Planning event is to plan the work for the Sprint, including creating a Sprint Goal, selecting and refining Product Backlog items, and developing a Sprint Backlog. If the work demands continuation of previous work, it will be done so but only when the items are picked from the Product Backlog and are in sync with the Sprint Goal.

Domain

Sprint Planning

Question 69

True or False: The Scrum Master is responsible for maintaining and updating the Product Backlog.

TRUE

Correct answer

FALSE

Overall explanation

The statement is false. The Scrum Master is not responsible for the Product Backlog.

Domain

Product Backlog

Question 70

Who is responsible for ensuring that the Scrum Team adheres to the Scrum values and principles?

Development Team

Correct answer

Scrum Master

Product Owner

Stakeholders

Overall explanation

The Scrum Master is responsible for ensuring that the Scrum Team adheres to the Scrum values and principles, promoting a culture of agility and continuous improvement.

Domain

Scrum Master Role

Question 71

Who has the authority to cancel a Sprint if it is the first Sprint of a new Product

Stakeholders

Scrum Master

Correct answer

Product Owner

Development Team

Overall explanation

A Sprint could be cancelled if the Sprint Goal becomes obsolete. Only the Product Owner has the authority to cancel the Sprint.

Domain

Sprint

Question 72

True or False: The management of the organization is responsible for ensuring that the Sprint Goal is met.

TRUE

Correct answer

FALSE

Overall explanation

The Product Owner, in collaboration with the Development Team, is responsible for working towards and ensuring that the Sprint Goal is met during the Sprint.

Domain

Product Owner

Question 73

The purpose of the Sprint Planning event is to identify how the previous Sprint outputs can be incorporated in the upcoming Sprint?

TRUE

Correct answer

FALSE

Overall explanation

The purpose of the Sprint Planning event is to define the Sprint Goal, select the Product Backlog items for the Sprint, and create a plan for achieving the Sprint Goal.

Domain

Sprint Planning

Question 74

True or False: When the Scrum Master feels work is not progressing well, the Scrum Maser can assign tasks to individual Development Team members.

TRUE

Correct answer

FALSE

Overall explanation

The statement is false. The Scrum Master does not assign tasks to individual Development Team members. The Development Team self-organizes and collaboratively determines how to complete the work.

Domain

Scrum Master Role

Question 75

What is the purpose of the Daily Scrum event in Scrum?

To plan the work for the day

Correct answer

To inspect and adapt the progress towards the Sprint Goal

To inspect and adapt the progress towards the Product Goal

To provide a status update to stakeholders

Overall explanation

The purpose of the Daily Scrum is to inspect and adapt the progress towards the Sprint Goal, foster collaboration, and identify any obstacles or adjustments needed to achieve the goal.

Domain

Daily Scrum

Question 76

True or False: The Scrum framework is not suitable for financial projects.

Correct answer

FALSE

TRUE

Overall explanation

The statement is false. While Scrum is widely used in software development, it can be applied to various types of projects beyond software development, including product development and other complex projects including financial projects.

Domain

Scrum Framework

Question 77

What is the purpose of the Sprint Burndown Chart in Scrum?

To track the team’s attendance at Scrum events

To track the number of completed Product Backlog items

Correct answer

To visualize the remaining work and progress in the Sprint

To estimate the effort required for each Product Backlog item

Overall explanation

The purpose of the Sprint Burndown Chart is to visualize the remaining work and progress in the Sprint, helping the team monitor their progress towards achieving the Sprint Goal.

Domain

Sprint Burndown Chart

Question 78

Who is responsible for ensuring that the Scrum Team is working in a self-organized and cross-functional manner?

Correct answer

Development Team

Stakeholders

Scrum Master

Product Owner

Overall explanation

The Development Team is responsible for working in a self-organized and cross-functional manner, collaborating to deliver high-quality increments of value.

Domain

Development Team

Question 79

In Scrum, who tracks the total remaining work in the Sprint Backlog?

Scrum Master

Product Owner

Stakeholders

Correct answer

Development Team

Overall explanation

The Development Team tracks the remaining work in the Sprint Backlog.

Domain

Sprint Backlog

Question 80

Who is responsible for ensuring that the Development Team understands the purpose and value of the work they undertake in a Sprint?

Correct answer

Development Team

Scrum Master

Stakeholders

Product Owner

Overall explanation

The Development Team is responsible for understanding the purpose and value of the work they undertake in a Sprint, ensuring their commitment and alignment with the Sprint Goal.

Domain

Development Team