PSM-I.004 Scrum Master Mock Exam Simulator 4
Scrum Master Mock Exam Simulator 4 – Results
Back to result overview
AttemptĀ 1
All domains
- 80 all
- 0 correct
- 0 incorrect
- 80
- 0 marked
Collapse all questions
Question 1
In Scrum, who is responsible for ensuring that the selected Product Backlog items meet the Definition of Ready?
Correct answer
Development Team
Product Owner
Scrum Master
Stakeholders
Overall explanation
The Development Team is responsible for ensuring that the selected Product Backlog items meet the Definition of Ready by collaborating with the Product Owner and clarifying any ambiguities.
Domain
Product Backlog
Question 2
True or False: The Scrum framework prescribes specific documentation requirements.
TRUE
Correct answer
FALSE
Overall explanation
The Scrum framework does not prescribe specific documentation requirements. It encourages capturing essential information while allowing flexibility based on the needs of the project.
Domain
Scrum Framework
Question 3
True or False: The Scrum framework prescribes specific tools or technologies to be used.
TRUE
Correct answer
FALSE
Overall explanation
The Scrum framework does not prescribe specific tools or technologies. It emphasizes the importance of individuals and interactions over tools and promotes adaptable approaches.
Domain
Scrum Framework
Question 4
In Scrum, who is responsible for ensuring that the selected Product Backlog items meet the Definition of Ready?
Correct answer
Development Team
Stakeholders
Scrum Master
Product Owner
Overall explanation
The Development Team is responsible for ensuring that the selected Product Backlog items meet the Definition of Ready by collaborating with the Product Owner and clarifying any ambiguities.
Domain
Product Backlog
Question 5
What is the maximum duration for a Sprint in Scrum when the team size is small.
It can vary depending on the nature of the project
Two weeks
One week
Correct answer
One month
Overall explanation
The maximum duration for a Sprint in Scrum is four weeks.
Domain
Sprint Duration
Question 6
True or False: The Product Owner is solely responsible for estimating the effort required to complete the Product Backlog items.
Correct answer
FALSE
TRUE
Overall explanation
Estimating the effort required to complete the Product Backlog items is a collaborative effort involving the Development Team and other stakeholders, not solely the Product Owner.
Domain
Product Owner
Question 7
What is the recommended frequency for holding the Sprint Retrospective event in Scrum when the same team is working together for more than 10 Sprints?
Every month
Every other Sprint
Every quarter
Correct answer
Every Sprint
Overall explanation
The Sprint Retrospective event should be held at the end of every Sprint to reflect on the previous Sprint and identify areas for improvement in the next Sprint.
Domain
Sprint Retrospective
Question 8
True or False: The Product Owner is responsible for assigning tasks to individual Development Team members when he/she feels work is not progressing well.
TRUE
Correct answer
FALSE
Overall explanation
The Product Owner does not assign tasks to individual Development Team members. The Development Team self-organizes and determines how to accomplish the work.
Domain
Scrum Master Role
Question 9
For big products, there can be two Product Owners within the same Scrum Team?
TRUE
Correct answer
FALSE
Overall explanation
There can only be one Product Owner within a Scrum Team.
Domain
Product Owner
Question 10
What is the purpose of the Sprint Retrospective event in Scrum?
To review and adjust the Product Backlog
Correct answer
To inspect and adapt the Scrum Team’s processes
To demonstrate the Increment to stakeholders
To plan the work for the next Sprint
Overall explanation
The purpose of the Sprint Retrospective is to inspect and adapt the Scrum Team’s processes, identify improvements, and plan adjustments for the next Sprint.
Domain
Sprint Retrospective
Question 11
Who is responsible for defining the Sprint Goal?
Development Team
Scrum Master
Product Owner
Correct answer
Scrum Team
Overall explanation
The entire Scrum Team, including the Product Owner, Development Team, and Scrum Master, collaboratively defines the Sprint Goal during the Sprint Planning event.
Domain
Sprint Goal
Question 12
True or False: The Scrum framework prescribes best practices, coding guidelines and leading industry standards that the Development Team must follow.
Correct answer
FALSE
TRUE
Overall explanation
The statement is false. The Scrum framework does not prescribe such things.
Domain
Scrum Framework
Question 13
Which statement best describes the concept of "Sprint Goal" in Scrum?
It is a target velocity to achieve by the end of the Sprint
Correct answer
It is a high-level objective or outcome for the Sprint
It is a detailed list of tasks for the Development Team to complete
It is the estimated amount of work that can be completed in the Sprint
Overall explanation
The Sprint Goal is a high-level objective or outcome that provides focus and coherence to the work undertaken in the Sprint.
Domain
Sprint Goal
Question 14
What is the purpose of the Sprint Planning event in Scrum?
To estimate the work required for the selected Product Backlog items
To create a detailed schedule for the Sprint
To update the Product Backlog with new items
Correct answer
To define the Sprint Goal and plan the work for the Sprint
Overall explanation
The purpose of the Sprint Planning event is to define the Sprint Goal, select the Product Backlog items for the Sprint, and create a plan for achieving the Sprint Goal.
Domain
Sprint Planning
Question 15
True or False: The Scrum framework prescribes specific software development practices.
TRUE
Correct answer
FALSE
Overall explanation
The Scrum framework does not prescribe specific software development practices. It is a framework that can be used with different software development approaches.
Domain
Scrum Framework
Question 16
True or False: The Scrum Master is a management position with authority over the Development Team.
Correct answer
FALSE
TRUE
Overall explanation
The statement is false. The Scrum Master is not a management position with authority over the Development Team. The Scrum Master serves as a servant-leader and facilitator for the Scrum Team.
Domain
Scrum Master Role
Question 17
True or False: The Development Team is responsible for coordinating with stakeholders and managing their expectations.
TRUE
Correct answer
FALSE
Overall explanation
The Development Team collaborates with stakeholders but is not responsible for coordinating with them or managing their expectations. This is primarily the role of the Product Owner.
Domain
Development Team
Question 18
In Scrum, who is responsible for prioritizing the Product Backlog?
Stakeholders
Correct answer
Product Owner
Scrum Master
Development Team
Overall explanation
The Product Owner is responsible for prioritizing the Product Backlog based on the value and insights from stakeholders and the Development Team.
Domain
Product Backlog
Question 19
True or False: The Development Team is responsible for selecting the items from the Product Backlog for the Sprint.
FALSE
Correct answer
TRUE
Overall explanation
The Development Team, in collaboration with the Product Owner, is responsible for selecting the items from the Product Backlog for the Sprint during the Sprint Planning event.
Domain
Development Team
Question 20
What is the purpose of the Sprint Review in Scrum?
To evaluate the performance of individual team members
To inspect the Increment and adapt the Product Backlog
To review and approve changes to the Product Backlog
Correct answer
To showcase the completed Increment to stakeholders
Overall explanation
The purpose of the Sprint Review is to showcase the completed Increment to stakeholders and gather feedback to adapt the Product Backlog.
Domain
Sprint Review
Question 21
True or False: The Scrum framework is suitable only for software development projects.
Correct answer
FALSE
TRUE
Overall explanation
Scrum can be applied to various types of projects beyond software development, including product development and other complex projects.
Domain
Scrum Framework
Question 22
What is the primary purpose of the Sprint Review in Scrum?
Correct answer
To showcase the completed Increment to stakeholders
To inspect the Increment and adapt the Product Backlog
To review and approve changes to the Product Backlog
To evaluate the performance of individual team members
Overall explanation
The primary purpose of the Sprint Review is to showcase the completed Increment to stakeholders and gather feedback to adapt the Product Backlog.
Domain
Sprint Review
Question 23
In Scrum, who is responsible for managing the progress of the work during a Sprint when it is the first Sprint for a new product?
Product Owner
Stakeholders
Correct answer
Development Team
Scrum Master
Overall explanation
The Development Team is responsible for managing the progress of the work during a Sprint and ensuring transparency of their progress to the stakeholders.
Domain
Development Team
Question 24
What is the recommended maximum duration for a Sprint Review for a Scrum Team having less than 9 developers.
Correct answer
1 hour
3 hours
2 hours
4 hours
Overall explanation
The recommended maximum duration for a Sprint Review is 1 hour. It allows for effective inspection and adaptation while ensuring the event does not become overly time-consuming.
Domain
Sprint Review
Question 25
Who is responsible for creating and maintaining the Sprint Backlog when the Development Team is less experienced?
Scrum Master
Correct answer
Development Team
Stakeholders
Product Owner
Overall explanation
The Development Team is responsible for creating and maintaining the Sprint Backlog, based on the selected Product Backlog items and their commitment to the Sprint Goal.
Domain
Sprint Backlog
Question 26
True or False: The Product Owner is solely responsible for maintaining and updating the Product Backlog and any collaboration is prohibited.
TRUE
Correct answer
FALSE
Overall explanation
The statement is false. While the Product Owner is primarily responsible for maintaining and updating the Product Backlog, it is a collaborative effort involving input from the Development Team and stakeholders.
Domain
Product Backlog
Question 27
True or False: The Scrum Master is responsible for assigning tasks to the Development Team members.
TRUE
Correct answer
FALSE
Overall explanation
The Scrum Master is not responsible for assigning tasks to the Development Team members. The team self-organizes and collaboratively determines how to accomplish the Sprint Backlog items.
Domain
Scrum Master Role
Question 28
True or False: The Scrum framework prescribes specific project management methodologies.
Correct answer
FALSE
TRUE
Overall explanation
The Scrum framework does not prescribe specific project management methodologies. It is a lightweight framework for agile product development.
Domain
Scrum Framework
Question 29
Who is responsible for making sure the Development Team understands the Product Goal and the Sprint Goal?
Stakeholders
Development Team
Scrum Master
Correct answer
Product Owner
Overall explanation
The Product Owner is responsible for making sure the Development Team understands the Product Goal and the Sprint Goal, ensuring alignment and clarity on the desired outcomes.
Domain
Product Owner
Question 30
True or False: The Sprint Backlog is a dynamic document that is updated throughout the Sprint as new information emerges.
Correct answer
TRUE
FALSE
Overall explanation
The statement is true. The Sprint Backlog is a dynamic document that is updated throughout the Sprint as new information emerges and the Development Team learns more.
Domain
Sprint Backlog
Question 31
In Scrum, who is responsible for managing the progress of the work during a Sprint when the organization has a dedicated Compliance Team?
Scrum Master
Correct answer
Development Team
Product Owner
Stakeholders
Overall explanation
The Development Team is responsible for managing the progress of the work during a Sprint and ensuring transparency of their progress to the stakeholders.
Domain
Development Team
Question 32
Who is responsible for managing the progress of the work during a Sprint?
Stakeholders
Product Owner
Correct answer
Development Team
Scrum Master
Overall explanation
The Development Team is responsible for managing the progress of the work during a Sprint and ensuring transparency of their progress to the stakeholders.
Domain
Development Team
Question 33
What is the primary purpose of the Daily Scrum in non-software development Scrum Teams.
To plan the work for the day
To evaluate the performance of individual team members
To provide a status update to the Product Owner
Correct answer
To identify any obstacles or impediments
Overall explanation
The primary purpose of the Daily Scrum is to identify any obstacles or impediments that may affect the Development Team’s progress and collaborate on finding solutions.
Domain
Daily Scrum
Question 34
True or False: The Scrum Master is responsible for ensuring that the Scrum Team has a clear understanding of the work to be done.
Correct answer
TRUE
FALSE
Overall explanation
The Scrum Master is responsible for ensuring that the Scrum Team has a clear understanding of the work to be done, facilitating effective communication and collaboration.
Domain
Scrum Master Role
Question 35
Who is responsible for removing any obstacles that hinder the progress of the Development Team?
Product Owner
Development Team
Stakeholders
Correct answer
Scrum Master
Overall explanation
The Scrum Master is responsible for removing obstacles that hinder the progress of the Development Team, facilitating their work and ensuring a productive and uninterrupted workflow.
Domain
Scrum Master Role
Question 36
Who is responsible for ensuring that the Development Team understands the purpose and value of the work they undertake in a Sprint?
Scrum Master
Correct answer
Development Team
Stakeholders
Product Owner
Overall explanation
The Development Team is responsible for understanding the purpose and value of the work they undertake in a Sprint, ensuring their commitment and alignment with the Sprint Goal.
Domain
Development Team
Question 37
The Development Team cant start work until the entire Product Backlog is complete.
Correct answer
FALSE
TRUE
Overall explanation
This is not correct. The Product Backlog is an emergent, ordered list of what is needed to improve the product. It is a live document that will always keep on changing.
Domain
Product Backlog
Question 38
What is the purpose of the Sprint Retrospective in Scrum?
To review and adapt the Sprint Backlog
Correct answer
To reflect on the team’s performance and identify improvements
To evaluate the performance of individual team members
To showcase the completed Increment to stakeholders
Overall explanation
The purpose of the Sprint Retrospective is to reflect on the team’s performance, identify areas of improvement, and create a plan for implementing changes in the next Sprint.
Domain
Sprint Retrospective
Question 39
Who is responsible for managing the Product Backlog during a Sprint?
Correct answer
Product Owner
Stakeholders
Scrum Master
Development Team
Overall explanation
The Product Owner is responsible for managing the Product Backlog during a Sprint, ensuring it is refined, reprioritized, and aligned with the Sprint Goal.
Domain
Product Backlog
Question 40
In Scrum, who is responsible for resolving conflicts and removing any impediments that hinder the Development Team’s progress?
Correct answer
Scrum Master
Product Owner
Stakeholders
Development Team
Overall explanation
The Scrum Master is responsible for resolving conflicts and removing any impediments that hinder the Development Team’s progress, enabling them to focus on delivering the Sprint Goal.
Domain
Scrum Master Role
Question 41
What is the recommended maximum duration for a Daily Scrum when held at the beginning of a working week.
45 minutes
30 minutes
Correct answer
15 minutes
1 hour
Overall explanation
The recommended maximum duration for a Daily Scrum is 15 minutes. It promotes focus, quick updates, and efficient coordination without consuming excessive time.
Domain
Daily Scrum
Question 42
Product Owner is supposed to be present for the Sprint Retrospective event.
TRUE
Correct answer
FALSE
Overall explanation
Product Owner participation is required for the Sprint Retrospective.
Domain
Sprint Retrospective
Question 43
Who is responsible for ensuring that the Development Team has the necessary skills and resources to achieve the Sprint Goal?
Stakeholders
Correct answer
Development Team
Scrum Master
Product Owner
Overall explanation
The Development Team is responsible for ensuring that they have the necessary skills and resources to achieve the Sprint Goal, fostering self-organization and continuous improvement.
Domain
Development Team
Question 44
True or False: The Scrum Master is a management position with authority over the Development Team.
TRUE
Correct answer
FALSE
Overall explanation
The Scrum Master is not a management position with authority over the Development Team. The Scrum Master serves as a servant-leader and facilitator for the Scrum Team.
Domain
Scrum Master Role
Question 45
Who is responsible for ensuring that the Scrum events are timeboxed and effectively conducted?
Development Team
Product Owner
Correct answer
Scrum Master
Stakeholders
Overall explanation
The Scrum Master is responsible for ensuring that the Scrum events are timeboxed and effectively conducted, enabling valuable collaboration and maximizing their purpose.
Domain
Scrum Master Role
Question 46
True or False: The Scrum framework prescribes specific engineering practices and techniques.
TRUE
Correct answer
FALSE
Overall explanation
The Scrum framework does not prescribe specific engineering practices and techniques. It focuses on the roles, events, artifacts, and values of Scrum.
Domain
Scrum Framework
Question 47
What is the recommended duration for a Sprint in Scrum involving a product to be launched in more than a year.
3 weeks
1 month
2 weeks
Correct answer
4 weeks
Overall explanation
The recommended duration for a Sprint in Scrum is 2 weeks. It allows for frequent inspection and adaptation while providing a reasonable timeframe for delivering valuable increments.
Domain
Sprint Duration
Question 48
When the Development Team has more developers, the daily Scrum Team duration would get changed?
Correct answer
FALSE
TRUE
Overall explanation
The number of Developers has no impact on the maximum duration (15 minutes) for the Daily Scrum.
Domain
Daily Scrum
Question 49
What is the purpose of the Sprint Review event in Scrum?
To inspect and adapt the progress towards the Sprint Goal
To review and adjust the Product Backlog
Correct answer
To demonstrate the Increment to stakeholders
To plan the work for the next Sprint
Overall explanation
The purpose of the Sprint Review is to demonstrate the Increment to stakeholders, gather feedback, and inspect and adapt the progress towards the Sprint Goal.
Domain
Sprint Review
Question 50
Who is responsible for ensuring that the Sprint Backlog is visible and up-to-date?
Product Owner
Scrum Master
Stakeholders
Correct answer
Development Team
Overall explanation
The Development Team is responsible for ensuring that the Sprint Backlog is visible and up-to-date, providing transparency on the progress and work remaining in the Sprint.
Domain
Sprint Backlog
Question 51
What is the purpose of the Sprint Retrospective in Scrum?
To review and adapt the Sprint Backlog
Correct answer
To reflect on the team’s performance and identify improvements
To evaluate the performance of individual team members
To showcase the completed Increment to stakeholders
Overall explanation
The purpose of the Sprint Retrospective is to reflect on the team’s performance, identify areas of improvement, and create a plan for implementing changes in the next Sprint.
Domain
Sprint Retrospective
Question 52
True or False: The Development Team can make changes to the selected Product Backlog items during a Sprint.
FALSE
Correct answer
TRUE
Overall explanation
The statement is true. The Development Team can make changes to the selected Product Backlog items during a Sprint if it helps to achieve the Sprint Goal and meets the Definition of Done.
Domain
Development Team
Question 53
Who is responsible for prioritizing the Product Backlog items?
Stakeholders
Scrum Master
Correct answer
Product Owner
Development Team
Overall explanation
The Product Owner is responsible for prioritizing the Product Backlog items, considering the needs of the stakeholders and maximizing the value delivered by the Scrum Team.
Domain
Product Backlog
Question 54
In Scrum, who is responsible for prioritizing the Product Backlog?
Development Team
Scrum Master
Correct answer
Product Owner
Stakeholders
Overall explanation
The Product Owner is responsible for prioritizing the Product Backlog based on the value and insights from stakeholders and the Development Team.
Domain
Product Backlog
Question 55
Who is responsible for conducting the Sprint Review event?
Scrum Master
Correct answer
Product Owner
Stakeholders
Development Team
Overall explanation
The Product Owner is responsible for conducting the Sprint Review event, facilitating the demonstration of the Increment to stakeholders and gathering their valuable feedback.
Domain
Sprint Review
Question 56
True or False: The Scrum framework prescribes specific engineering practices and technical practices that the Development Team must follow.
Correct answer
FALSE
TRUE
Overall explanation
The statement is false. The Scrum framework does not prescribe specific engineering or technical practices. The Development Team is responsible for selecting and implementing appropriate practices.
Domain
Scrum Framework
Question 57
Who is responsible for managing the Product Backlog and ensuring that it is transparent, ordered, and properly refined?
Scrum Master
Stakeholders
Development Team
Correct answer
Product Owner
Overall explanation
The Product Owner is responsible for managing the Product Backlog and ensuring its transparency, order, and refinement to maximize value delivery.
Domain
Product Backlog
Question 58
Who is responsible for ensuring that the Sprint Backlog is visible and up-to-date?
Scrum Master
Stakeholders
Product Owner
Correct answer
Development Team
Overall explanation
The Development Team is responsible for ensuring that the Sprint Backlog is visible and up-to-date, providing transparency on the progress and work remaining in the Sprint.
Domain
Sprint Backlog
Question 59
Who has the authority to cancel a Sprint when the Sprint Goal becomes obsolete.
Scrum Master
Correct answer
Product Owner
Development Team
Stakeholders
Overall explanation
A Sprint could be cancelled if the Sprint Goal becomes obsolete. Only the Product Owner has the authority to cancel the Sprint.
Domain
Sprint
Question 60
Who is responsible for ensuring that the Scrum Team understands and adheres to the Scrum framework?
Scrum Master and Project Management Office
Scrum Master and Human Resources Department
Correct answer
Scrum Master
Scrum Master and Product Owner
Overall explanation
The Scrum Master is responsible for ensuring that the Scrum Team understands and adheres to the Scrum framework, facilitating its implementation and guiding the team’s adoption.
Domain
Scrum Master Role
Question 61
Who is responsible for managing the Product Backlog in Scrum?
Stakeholders
Correct answer
Product Owner
Scrum Master
Development Team
Overall explanation
The Product Owner is responsible for managing the Product Backlog, including its content, ordering, and ensuring its transparency to stakeholders.
Domain
Product Backlog
Question 62
When should the increment be released.
At the conclusion of a Sprint
When increment is ready
Correct answer
When the Scrum Teams decides to release
When market conditions are good
Overall explanation
When the Scrum Team decides, the increment can be released.
Domain
Development Team
Question 63
Which statement best describes the concept of "Sprint Goal" in Scrum?
It is a measure of success of how the organization is progressing.
Correct answer
It communicates why the Sprint is of value to its customers and/or users.
It is the estimated amount of work that can be completed in the Sprint
It is a detailed list of tasks for the Development Team to complete
Overall explanation
The Sprint Goal is a high-level objective or outcome that provides focus and coherence to the work undertaken in the Sprint.
Domain
Sprint Goal
Question 64
Who is responsible for ensuring that the Sprint Retrospective is conducted and its outcomes are acted upon?
Development Team
Product Owner
Correct answer
Scrum Master
Stakeholders
Overall explanation
The Scrum Master is responsible for ensuring that the Sprint Retrospective is conducted and its outcomes are acted upon, promoting continuous improvement and adaptation.
Domain
Scrum Master Role
Question 65
During a Sprint, the Development Team determines that it won’t be able to complete all the selected Product Backlog items. What should the Development Team do?
Correct answer
Inform the Product Owner and negotiate new commitments
Extend the Sprint duration to accommodate the remaining work
Skip those items and continue with the Sprint
Add the unfinished items to the next Sprint
Overall explanation
The Development Team should inform the Product Owner and negotiate new commitments based on the capacity and available time in the Sprint.
Domain
Sprint Planning
Question 66
True or False: The Scrum framework can be applied to any project or product development effort.
FALSE
Correct answer
TRUE
Overall explanation
The Scrum framework is flexible and can be applied to various project or product development efforts, enabling iterative and incremental delivery.
Domain
Scrum Framework
Question 67
True or False: The Sprint Review is an opportunity for the Development Team to inspect and adapt their working methods.
TRUE
Correct answer
FALSE
Overall explanation
The statement is false. The Sprint Retrospective provides an opportunity for the Scrum Team to inspect their working methods, gather feedback, and identify areas for improvement in the next Sprint.
Domain
Sprint Review
Question 68
Sprint Planning event in Scrum is an opportunity to find ways how can previous discontinued work be continued in the current Sprint.
TRUE
Correct answer
FASLE
Overall explanation
The purpose of the Sprint Planning event is to plan the work for the Sprint, including creating a Sprint Goal, selecting and refining Product Backlog items, and developing a Sprint Backlog. If the work demands continuation of previous work, it will be done so but only when the items are picked from the Product Backlog and are in sync with the Sprint Goal.
Domain
Sprint Planning
Question 69
True or False: The Scrum Master is responsible for maintaining and updating the Product Backlog.
TRUE
Correct answer
FALSE
Overall explanation
The statement is false. The Scrum Master is not responsible for the Product Backlog.
Domain
Product Backlog
Question 70
Who is responsible for ensuring that the Scrum Team adheres to the Scrum values and principles?
Development Team
Correct answer
Scrum Master
Product Owner
Stakeholders
Overall explanation
The Scrum Master is responsible for ensuring that the Scrum Team adheres to the Scrum values and principles, promoting a culture of agility and continuous improvement.
Domain
Scrum Master Role
Question 71
Who has the authority to cancel a Sprint if it is the first Sprint of a new Product
Stakeholders
Scrum Master
Correct answer
Product Owner
Development Team
Overall explanation
A Sprint could be cancelled if the Sprint Goal becomes obsolete. Only the Product Owner has the authority to cancel the Sprint.
Domain
Sprint
Question 72
True or False: The management of the organization is responsible for ensuring that the Sprint Goal is met.
TRUE
Correct answer
FALSE
Overall explanation
The Product Owner, in collaboration with the Development Team, is responsible for working towards and ensuring that the Sprint Goal is met during the Sprint.
Domain
Product Owner
Question 73
The purpose of the Sprint Planning event is to identify how the previous Sprint outputs can be incorporated in the upcoming Sprint?
TRUE
Correct answer
FALSE
Overall explanation
The purpose of the Sprint Planning event is to define the Sprint Goal, select the Product Backlog items for the Sprint, and create a plan for achieving the Sprint Goal.
Domain
Sprint Planning
Question 74
True or False: When the Scrum Master feels work is not progressing well, the Scrum Maser can assign tasks to individual Development Team members.
TRUE
Correct answer
FALSE
Overall explanation
The statement is false. The Scrum Master does not assign tasks to individual Development Team members. The Development Team self-organizes and collaboratively determines how to complete the work.
Domain
Scrum Master Role
Question 75
What is the purpose of the Daily Scrum event in Scrum?
To plan the work for the day
Correct answer
To inspect and adapt the progress towards the Sprint Goal
To inspect and adapt the progress towards the Product Goal
To provide a status update to stakeholders
Overall explanation
The purpose of the Daily Scrum is to inspect and adapt the progress towards the Sprint Goal, foster collaboration, and identify any obstacles or adjustments needed to achieve the goal.
Domain
Daily Scrum
Question 76
True or False: The Scrum framework is not suitable for financial projects.
Correct answer
FALSE
TRUE
Overall explanation
The statement is false. While Scrum is widely used in software development, it can be applied to various types of projects beyond software development, including product development and other complex projects including financial projects.
Domain
Scrum Framework
Question 77
What is the purpose of the Sprint Burndown Chart in Scrum?
To track the team’s attendance at Scrum events
To track the number of completed Product Backlog items
Correct answer
To visualize the remaining work and progress in the Sprint
To estimate the effort required for each Product Backlog item
Overall explanation
The purpose of the Sprint Burndown Chart is to visualize the remaining work and progress in the Sprint, helping the team monitor their progress towards achieving the Sprint Goal.
Domain
Sprint Burndown Chart
Question 78
Who is responsible for ensuring that the Scrum Team is working in a self-organized and cross-functional manner?
Correct answer
Development Team
Stakeholders
Scrum Master
Product Owner
Overall explanation
The Development Team is responsible for working in a self-organized and cross-functional manner, collaborating to deliver high-quality increments of value.
Domain
Development Team
Question 79
In Scrum, who tracks the total remaining work in the Sprint Backlog?
Scrum Master
Product Owner
Stakeholders
Correct answer
Development Team
Overall explanation
The Development Team tracks the remaining work in the Sprint Backlog.
Domain
Sprint Backlog
Question 80
Who is responsible for ensuring that the Development Team understands the purpose and value of the work they undertake in a Sprint?
Correct answer
Development Team
Scrum Master
Stakeholders
Product Owner
Overall explanation
The Development Team is responsible for understanding the purpose and value of the work they undertake in a Sprint, ensuring their commitment and alignment with the Sprint Goal.
Domain
Development Team