PSM-I.001.057
January 12, 2025
Question 57
Who is responsible for managing the progress of work during a Sprint?
Stakeholders
Development Team
Scrum Master
Product Owner
Overall explanation
The Development Team is responsible for managing the progress of work during a Sprint, using the Sprint Backlog and Scrum artifacts.
Domain
Roles