Question 57

Who is responsible for managing the progress of work during a Sprint?

Stakeholders

Development Team

Scrum Master

Product Owner

Overall explanation

The Development Team is responsible for managing the progress of work during a Sprint, using the Sprint Backlog and Scrum artifacts.

Domain

Roles