PSM-I.001.066
January 12, 2025
Question 66
True or False: The Scrum Team should strive to deliver a potentially releasable Increment of the product at the end of each Sprint.
FALSE
TRUE
Overall explanation
The Scrum Team should strive to deliver a potentially releasable Increment of the product at the end of each Sprint. The Increment should meet the Definition of Done and be in a usable condition, even if the Product Owner decides not to release it.
Domain
Scrum Principles