HomeScrum.orgPSM I[PSM I] Question #001PSM-I.001.012 What is the maximum duration for a Sprint in Scrum?

PSM-I.001.012 What is the maximum duration for a Sprint in Scrum?

January 12, 2025
Question 12

What is the maximum duration for a Sprint in Scrum?

  • 1 week

  • 3 weeks

  • 2 weeks

  • 4 weeks

Overall explanation

In Scrum, a sprint is a time-boxed event of one to four weeks in which your Scrum team focuses only on a sprint goal.

Domain

Sprint