PSM-I.001.059

Question 59

A stakeholder requests to observe the Daily Scrum to better understand the progress of the Development Team. What should the Scrum Team do in response to this request?

Invite the stakeholder to attend the Daily Scrum as an observer without disrupting the event.

Discuss the request with the Product Owner and seek their guidance.

Explain to the stakeholder that the Daily Scrum is an internal event for the Development Team.

Offer alternative ways for the stakeholder to gain visibility into the team’s progress.

Overall explanation

In this scenario, the Scrum Team should explain to the stakeholder that the Daily Scrum is an internal event for the Development Team. They can offer alternative ways for the stakeholder to gain visibility, such as periodic updates or separate sessions. If the stakeholder’s presence is deemed beneficial, they can be invited as an observer without disrupting the event. Discussing with the Product Owner can provide further guidance.

Domain

Scrum