Category: PSM I

PSM-I.001.061

Question 61 True or False: In Scrum, the Product Owner and the Scrum Master roles can be combined. FALSE TRUE Overall explanation The Scrum Guide...

PSM-I.001.062

Question 62 The Development Team is unable to complete all the committed Product Backlog items by the end of the Sprint due to unforeseen challenges....

PSM-I.001.063

Question 63 True or False: The Scrum Master is responsible for ensuring that the Daily Scrum occurs at the same time every day. TRUE FALSE...

PSM-I.001.064

Question 64 The Sprint Backlog is owned by Developers. FALSE TRUE Overall explanation The Developers own the Sprint Backlog and they are responsible and totally...

PSM-I.001.065

Question 65 During the Daily Scrum, a Development Team member raises an issue that requires immediate attention from the Scrum Master and Product Owner. What...

PSM-I.001.066

Question 66 True or False: The Scrum Team should strive to deliver a potentially releasable Increment of the product at the end of each Sprint....

PSM-I.001.067

Question 67 True or False: The Sprint Review is an opportunity for the Scrum Team to inspect the Increment and adapt the Product Backlog accordingly....

PSM-I.001.068

Question 68 The Development Team is consistently unable to complete the selected Product Backlog items within the Sprint time frame. What should the Scrum Master...

PSM-I.001.069

Question 69 What is the recommended maximum size for a Development Team in Scrum? There is no specific recommendation. 10 5 15 Overall explanation There...

PSM-I.001.070

Question 70 True or False: The Daily Scrum should be time-boxed to a maximum of 15 minutes, regardless of the number of Development Team members....